Digital infrastructure: AI data-center campus buildout · Vérifié le 2026-10-30
Seule l’étape rapportée est mise en évidence. Les chiffres et dates distinguent les projets des faits démontrés.
Epoch’s current campus estimate: 237 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 237 MW”
Physical-stage observation dated 2026-05-04. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Building 5 steel framing is underway.”
Epoch’s dated 2026-05-04 assessment: Building 5 steel framing is underway. Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Building 5 steel framing is underway.”
Epoch estimates AI hardware: Google TPU v4, Google TPU v5e, and Google TPU v5p chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Google TPU v4, Google TPU v5e, and Google TPU v5p chips.”
Epoch dated observation: Land clearing begins for Building 1 of expansion.
“Land clearing begins for Building 1 of expansion.”
Epoch dated observation: Building 4 shell mostly complete, Building 5 steel framing is underway.
“Building 4 shell mostly complete, Building 5 steel framing is underway.”
Photos de lecteurs, distinctes des médias sourcés du pin. Notez ce que vous avez mangé ou vu et, sur un pin de restaurant, identifiez les plats directement sur votre photo.
La première entrée est toujours la source de l’épingle. La confiance globale est une moyenne pondérée de la fermeté avec laquelle chaque référence étaye les heures de début et de fin retenues ci-dessus ; une référence compte moitié moins pour chaque tranche de 180 jours d’ancienneté par rapport à la plus récente.
La date enregistrée est un marqueur de suivi ou de trajectoire de capacité estimé, et non un jour d'ouverture exact vérifié. L'état de la construction suit la portée physique datée citée ; aucun achèvement n’est déduit des objectifs écoulés.
Construction research 2026-10-24: Epoch’s[1] 2026-05-04 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Building 5 steel framing is underway.” Dated observation 2026-05-04; future trajectory rows and modeled costs are distinguished from this physical milestone.
Il manque quelque chose ou une erreur s'est glissée ? Dites-le avec vos mots : un lien qui étaye cette épingle, une autre date de début ou de fin et pourquoi, ou une information absente ou erronée. L'IA la vérifie au regard des sources de l'épingle, en cherche de meilleures et ajoute toute page qui vous donne raison. Les sources de l'épingle restent celles qui comptent le plus. L'IA regarde aussi les images : une image qui montre autre chose, ou qui le montre mal, passe en dernier ou est remplacée.
Titre original: Google Papillion AI Data Center Buildout
L’observation d’Epoch du 04/05/2026 documente la construction/installation physique restante pour cette construction nommée. In Progress ne complète pas les bâtiments opérationnels antérieurs ni la capacité future. Les décomptes de puissance et d’accélérateur restent des estimations d’époque, et non une évaluation certifiée par l’opérateur. Les coûts d’investissement modélisés en dollars 2025 incluent le matériel informatique et ne constituent pas un budget de construction natif.
Campus de formation et d'inférence d'IA frontalière à grande échelle suivi par Epoch AI avec des empreintes satellite annotées (15 parties physiques).