Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · source
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · source
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · source
| Date | Observed status |
|---|---|
| 2023-10-31 | Start of construction for the first building, according to [Applied Digital](https://ir.applieddigital.com/news-events/press-releases/detail/75/applied-digital-announces-groundbreaking-of). CoreWeave |
| 2025-05-28 | CoreWeave signed the first lease package for 250 MW. No buildings online yet. This is according to an [SEC 8-k filing](https://www.sec.gov/Archives/edgar/data/1144879/000164117225013199/form8-k.htm) f |
| 2025-08-29 | [A new 150 MW lease](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with) brings CoreWeave to 400 MW total contracted. The project |
| 2025-10-27 | The first 50 MW slice of Building 1 has reached Ready for Service status according to [this report](https://ir.applieddigital.com/news-events/press-releases/detail/133/applied-digital-achieves-ready-f |
| 2025-11-24 | [This Applied Digital report](https://ir.applieddigital.com/news-events/press-releases/detail/137/applied-digital-completes-phase-ii-ready-for-service-at) says the rest of Building 1 has reached Ready |
| 2026-03-27 | According to satellite imagery, Building 1 looks complete and in service, with the surrounding power/cooling equipment also operational. (Note: this image doesn't provide a view of buildings 2 or 3, t |
| 2026-06-30 | According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and |
| 2026-12-31 | According to the [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 2 should be online sometime in the seco |
| 2027-06-01 | According to [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 3 should come online in the first half of 2 |
Epoch AI satellite-imagery notes, in date order. · source
En construction
Digital infrastructure: AI data-center campus buildout · Vérifié le 2026-10-30
Seule l’étape rapportée est mise en évidence. Les chiffres et dates distinguent les projets des faits démontrés.
Epoch’s current campus estimate: 68 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 68 MW”
Physical-stage observation dated 2026-06-30. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Building 3 construction is well underway”
Epoch’s dated 2026-06-30 assessment: Building 3 construction is well underway Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Building 3 construction is well underway”
Epoch estimates AI hardware: Nvidia B200 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Nvidia B200 chips.”
Epoch dated observation: CoreWeave was not leased yet at this site, but this is the…
“CoreWeave was not leased yet at this site, but this is the construction start date we're using for relevance.”
Epoch dated observation: According to satellite imagery, Building 2 is fully roofed and shell…
“According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed.”
Photos de lecteurs, distinctes des médias sourcés du pin. Notez ce que vous avez mangé ou vu et, sur un pin de restaurant, identifiez les plats directement sur votre photo.
La première entrée est toujours la source de l’épingle. La confiance globale est une moyenne pondérée de la fermeté avec laquelle chaque référence étaye les heures de début et de fin retenues ci-dessus ; une référence compte moitié moins pour chaque tranche de 180 jours d’ancienneté par rapport à la plus récente.
La date enregistrée est un marqueur de suivi ou de trajectoire de capacité estimé, et non un jour d'ouverture exact vérifié. L'état de la construction suit la portée physique datée citée ; aucun achèvement n’est déduit des objectifs écoulés.
Construction research 2026-10-24: Epoch’s[1] 2026-06-30 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Building 3 construction is well underway” Dated observation 2026-06-30; future trajectory rows and modeled costs are distinguished from this physical milestone.
Il manque quelque chose ou une erreur s'est glissée ? Dites-le avec vos mots : un lien qui étaye cette épingle, une autre date de début ou de fin et pourquoi, ou une information absente ou erronée. L'IA la vérifie au regard des sources de l'épingle, en cherche de meilleures et ajoute toute page qui vous donne raison. Les sources de l'épingle restent celles qui comptent le plus. L'IA regarde aussi les images : une image qui montre autre chose, ou qui le montre mal, passe en dernier ou est remplacée.
Titre original: CoreWeave Ellendale ND AI Data Center Buildout
L’observation d’Epoch du 30/06/2026 documente la construction/installation physique restante pour cette construction nommée. In Progress ne complète pas les bâtiments opérationnels antérieurs ni la capacité future. Les décomptes de puissance et d’accélérateur restent des estimations d’époque, et non une évaluation certifiée par l’opérateur. Les coûts d’investissement modélisés en dollars 2025 incluent le matériel informatique et ne constituent pas un budget de construction natif.
Campus de formation et d'inférence d'IA de frontière hyperscale suivi par Epoch AI avec des empreintes satellite annotées (8 parties physiques).