ITER Starts Research Operations
- The 2024 baseline sets the start of research operations at 2034, inaugurating a 27-month period of hydrogen and deuterium plasma experimentation[2]
- Full magnetic energy and plasma current operation at 15 MA follows in 2036, and the deuterium-tritium phase in 2039[2]
- The original schedule had envisaged a first plasma as early as 2025; ITER's director-general attributed the change to the pandemic, quality issues and over-optimistic planning for a first-of-a-kind project[2]
- ITER stresses the new baseline is not directly comparable with the original schedule, because the milestones it names are different ones[2]
- The proposal went to the ITER Council in June 2024 and now serves as the working reference schedule[1]
References 268% CONFIDENCE
The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
- [1]50%iter.org/node/20687/updated-baseline-presentediter.org· Posted Sep 21, 2026· Starts Dec 31, 2034 ✓· 50% of score
ITER's updated 2024 baseline gives 2034 for the start of research activities. Only the year is stated, so the pin takes its last day.
- [2]85%New ITER schedule - Max Planck Institute for Plasma Physicsipp.mpg.de· Added Sep 21, 2026· 50% of score
A partner institute's summary of the 2024 baseline's milestone dates; read in this run.[1]
Suggest a correction
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.