La première entrée est toujours la source de l’épingle. La confiance globale est une moyenne pondérée de la fermeté avec laquelle chaque référence étaye les heures de début et de fin retenues ci-dessus ; une référence compte moitié moins pour chaque tranche de 180 jours d’ancienneté par rapport à la plus récente.
Stated as done, per babcock.com[6]: "(AKRON, Ohio - November 4, 2025) - Babcock & Wilcox ... announced today that it has ... [signed] an agreement for a limited notice to proceed"; the Business Wire copy on Yahoo Finance is timestamped 22:28 UTC and the SEC[2][3][5] 8-K was accepted at 17:31 ET.
B&W's filed August 2026 presentation: the $2.4B, 1.2 GW Base Electron project "will be located near Center, North Dakota" and its Conditional Use Permit was submitted in August 2026, with potential for another 1.2 GW.[1]
Applied Digital's 10-Q: the 4 November 2025 B&W warrant agreement, the 26 February 2026 Design-Build Agreement between Base Electron and B&W, Applied Digital's guarantee of Base Electron's obligations and its ~10% stake in Base Electron.[1]
Power Engineering coverage of the LNTP: four 300 MW natural gas-fired boiler and steam turbine plants for Applied Digital, operation targeted in 2028, full contract release expected in Q1 2026.[1]
The release as filed with the SEC[2][3] on 4 November 2025 (accepted 17:31 ET): LNTP for a project "valued at over $1.5 billion" to deliver one gigawatt for an Applied Digital AI Factory, four 300 MW gas-fired plants, operation targeted in 2028.
Il manque quelque chose ou une erreur s'est glissée ? Dites-le avec vos mots : un lien qui étaye cette épingle, une autre date de début ou de fin et pourquoi, ou une information absente ou erronée. L'IA la vérifie au regard des sources de l'épingle, en cherche de meilleures et ajoute toute page qui vous donne raison. Les sources de l'épingle restent celles qui comptent le plus.