पहली एंट्री हमेशा पिन का सोर्स होती है। कुल कॉन्फ़िडेंस एक भारित औसत है कि हर संदर्भ ऊपर इस्तेमाल किए गए शुरू और खत्म होने के समय का कितनी मज़बूती से समर्थन करता है; सबसे नए संदर्भ से हर 180 दिन पुराना होने पर किसी संदर्भ की गिनती आधी हो जाती है।
पहली इमारत का शिलान्यास अगस्त 2025 (सटीक माह) में हुआ था। क्यूटीएस के प्रकाशित लक्ष्य केवल वर्ष (चरण एक 2026, चरण दो 2027) हैं, इसलिए समाप्ति तिथि शून्य है; एपोच प्रोजेक्ट्स बिल्डिंग 4-7 का संचालन 15 नवंबर 2027 को होगा।
Construction research 2026-10-24: Epoch’s[1] 2026-05-07 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “the eastern Building 7 foundation is still underway” Dated observation 2026-05-07; future trajectory rows and modeled costs are distinguished from this physical milestone.
Cited in the project timeline.[1]
Cited in the project timeline.[1]
Cited in the project timeline.[1]
| 2025-10-27 | Building 1 roof complete, with air-cooled chillers in place. Building 2 and 3 roofs are partly completed. Building 4 and 5 have a foundation. |
|---|
| 2026-04-16 | Based on satellite imagery, the Buildings 1-3 shells look complete. Buildings 4-6 are far along, with roofs largely in place, while the eastern Building 7 foundation is well underway. No buildings ope |
|---|
| 2026-05-07 | Similar to April, Buildings 1-3 shells look complete. Buildings 4-6 are still far along, and the eastern Building 7 foundation is still underway. |
|---|
| 2026-10-23 | Buildings 1–3 look externally complete, with the air-cooled chillers fully installed, and surrounding yard work cleared. The many cars and trucks parked beside the buildings suggest commissioning is s |
|---|
| 2026-12-01 | Buildings 1-3 are operational. Based on the visible progress in the October satellite image, and the expected completion date reported by [local news](https://corridorbusiness.com[4][5][6][7]/scope-of-qts-data-pr |
|---|
| 2027-11-15 | Buildings 4-7 are operational. Based on the expected completion date reported by [local news](https://corridorbusiness.com[4][5][6][7]/scope-of-qts-data-project-in-cedar-rapids-continuing-to-grow/): “A QTS spokes |
|---|
Epoch AI satellite-imagery notes, in date order. · स्रोत
More than 2,000 construction and permanent jobs
“The project is expected to support more than 2,000 construction and permanent jobs.”
Seven buildings of 400,000 to 1.2 million sq ft each
“individual buildings ranging from 400,000 to 1.2 million square feet”
612 acres
“The campus will feature seven data center buildings on 612 acres”
1,133 MW IT
“supported by 1,133 MW of IT power”
Under construction; Buildings 1-3 externally complete, in commissioning
“we're not counting any buildings operational yet”
Land clearing begins for Buildings 1-3 (satellite)
“Land clearing begins for Building 1-3.”
City council authorizes development agreement
“authorized a formal development agreement for the Quality Technology Services (QTS) data center project”
QTS announces $10 billion campus in lieu of groundbreaking ceremony
“The project is estimated to have an overall investment of $10 billion over the course of its development”
Ground broken on first building
“Ground was broken on the first building in August”
Topping out of first three buildings
“marked the topping out of the first three buildings at the company's Cedar Rapids data center campus Tuesday, Oct. 21”
Linn County approves road use agreement
“In late October, the Linn County Board of Supervisors approved a road use agreement requiring QTS to provide over $117,000 in back payment for road damage”
Buildings 1-3 shells look complete (satellite)
“Based on satellite imagery, the Buildings 1-3 shells look complete.”
Energy Secretary Chris Wright tours construction site
“U.S. Energy Secretary Chris Wright toured the QTS data center construction site in southwest Cedar Rapids on Thursday”
Buildings 1-3 externally complete, commissioning underway (satellite)
“The many cars and trucks parked beside the buildings suggest commissioning is still underway, so we're not counting any buildings operational yet.”
Phase one completion target
“Construction is planned in two phases, with the first phase expected to be completed in 2026 and the second phase in 2027.”
Phase two completion target (full campus)
“Construction is planned in two phases, with the first phase expected to be completed in 2026 and the second phase in 2027.”
कुछ छूट गया या गलत है? अपने शब्दों में बताएं: कोई लिंक जो इस पिन का समर्थन करता हो, कोई अलग शुरुआत या खत्म होने की तारीख और उसकी वजह, या कोई तथ्य जो छूट गया हो या गलत हो। AI इसे इस पिन के सोर्स से मिलाकर जांचता है, बेहतर सोर्स खोजता है, और जो भी पेज आपकी बात का समर्थन करता है उसे जोड़ देता है। पिन के अपने सोर्स की अहमियत फिर भी सबसे ज़्यादा रहती है। AI तस्वीरें भी देखता है: जो तस्वीर कुछ और दिखाती हो या ठीक से न दिखाती हो, उसे नीचे कर दिया जाता है या बदल दिया जाता है।
मूल शीर्षक: QTS Cedar Rapids AI Data Center Buildout
क्यूटीएस, एक ब्लैकस्टोन कंपनी, दक्षिण पश्चिम सीडर रैपिड्स, आयोवा में एलियंट एनर्जी के बिग सीडर इंडस्ट्रियल सेंटर की 612 एकड़ जमीन पर सात-बिल्डिंग डेटा सेंटर परिसर का निर्माण कर रही है, जिसमें कुल अनुमानित $ 10 बिलियन का निवेश है। अगस्त 2025 में पहली इमारत को तोड़ दिया गया था, पहली तीन इमारतें अक्टूबर 2025 में शीर्ष पर थीं और एपोच की अक्टूबर 2026 की इमेजरी उन्हें बाहरी रूप से पूर्ण दिखाती है लेकिन अभी भी चालू हो रही है। क्यूटीएस ने 2026 में चरण एक और 2027 में चरण दो का लक्ष्य रखा है।
एपोच के 2026-05-07 अवलोकन दस्तावेज़ इस नामित बिल्डआउट के लिए शेष भौतिक निर्माण/स्थापना हैं। प्रगति में पहले से संचालित भवन या भविष्य की क्षमता पूरी नहीं होती है। पावर और एक्सेलेरेटर की गणना एपोच अनुमान ही रहती है, ऑपरेटर-प्रमाणित रेटिंग नहीं। मॉडल की गई 2025-डॉलर की पूंजीगत लागत में कंप्यूट हार्डवेयर शामिल है और यह स्रोत-मूल निर्माण बजट नहीं है।
हाइपरस्केल फ्रंटियर एआई प्रशिक्षण और अनुमान परिसर को एनोटेटेड उपग्रह पदचिह्न (10 भौतिक भागों) के साथ एपोच एआई द्वारा ट्रैक किया गया।