Documented physical milestone or dated progress/reporting marker. Period-end dates represent only the reported month/quarter; they do not invent an exact operation date. Source estimates are labelled and not treated as confirmed future opening dates.
Baltic Power[3][5] monopile installation image supplied with ORLEN’s February 2026 foundations-complete announcement.
Published project-specific cost for Baltic Power[5]: EUR 4.05e+09. Basis: Published project capex including insurance, excluding the separately described financing/reserve components. Published electric generating project rating for Baltic Power: 1140 MW. Basis: 76 operator-reported turbines × 15 MW; corroborated by inventory rating.
Northland Q2 2026 update confirms Baltic Power[3][5] first power, 61 of 76 turbines installed, 15 generating and construction/commissioning ongoing. Full commercial operations remain a second-half 2026 target; costs are aligned with original expectations.
Operator forecasts 4,000 GWh yearly electricity production; this is expected annual energy, distinct from rated MW.[1]
कुछ छूट गया या गलत है? अपने शब्दों में बताएं: कोई लिंक जो इस पिन का समर्थन करता हो, कोई अलग शुरुआत या खत्म होने की तारीख और उसकी वजह, या कोई तथ्य जो छूट गया हो या गलत हो। AI इसे इस पिन के सोर्स से मिलाकर जांचता है, बेहतर सोर्स खोजता है, और जो भी पेज आपकी बात का समर्थन करता है उसे जोड़ देता है। पिन के अपने सोर्स की अहमियत फिर भी सबसे ज़्यादा रहती है। AI तस्वीरें भी देखता है: जो तस्वीर कुछ और दिखाती हो या ठीक से न दिखाती हो, उसे नीचे कर दिया जाता है या बदल दिया जाता है।
Baltic Power publishes approximately €4.05 billion capital expenditure including insurance within an approximately €4.73 billion total budget. The larger budget also includes financing costs and reserve; the €4.4 billion credit package is not used as construction cost. The generating project has 76 turbines rated 15 MW each, totaling 1,140 MW; it is reported under construction in the August inventory.[3][4][5]
Published project-specific cost for Baltic Power: EUR 4.05e+09. Basis: Published project capex including insurance, excluding the separately described financing/reserve components. Published electric generating project rating for Baltic Power: 1140 MW. Basis: 76 operator-reported turbines × 15 MW; corroborated by inventory rating.[3]
Northland Q2 2026 update confirms Baltic Power first power, 61 of 76 turbines installed, 15 generating and construction/commissioning ongoing. Full commercial operations remain a second-half 2026 target; costs are aligned with original expectations.[4]
Operator forecasts 4,000 GWh yearly electricity production; this is expected annual energy, distinct from rated MW.[5]
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Baltic Power monopile installation image supplied with ORLEN’s February 2026 foundations-complete announcement. Credit: ORLEN / Baltic Power; photographer not named. Source and gallery; original media.