Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
| Date | Observed status |
|---|---|
| 2023-01-01 | Land clearing begins, with the east campus being the first of the three. Land clearing begins for the other two campuses months after. |
| 2025-01-01 | The first building is operational. On the north campus, building 4 is operational assuming a 3-month fit-out post structural completion. |
| 2025-03-01 | Three buildings are operational. On the west campus, building 1 is operational, and on the east campus, building 7 is operational. The second building on the east campus has installed generators, but |
| 2025-11-01 | Four buildings are operational. On the west campus, building 2 is operational assuming a 3-month fit-out post structural completion. |
| 2026-01-24 | Four buildings are operational in total. A fifth building, building 5 on the north campus, is finishing installing roofside cooling. Another building on the east campus is complete but does not have s |
| 2026-06-01 | Four buildings are operational. On the north campus, building 5 is nearing structural completion but still has roofing and cooling remaining. |
| 2026-08-06 | On the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars. Building 6, a much larger building across the pond, should finish construction in |
| 2026-11-01 | Five buildings are operational. On the north campus, building 5 is operational assuming a 3-month fit-out post structural completion. |
| 2026-12-31 | Six buildings are operational. On the north campus, building 6, the larger building, is operational assuming a 3-month fit-out if it is structurally complete in September. We assume Building 6 is abou |
| 2027-12-01 | All eight AI buildings are operational. Buildings 3 and 9 are assumed to be 1.25x the power and compute of buildings 1 and 7 based on the sizing of the backup generator enclosures; building 8 is exclu |
Epoch AI satellite-imagery notes, in date order. · sumber
Dalam pembangunan
Digital infrastructure: AI data-center campus buildout · Diperiksa 2026-10-30
Hanya tahap yang dilaporkan yang disorot. Angka dan tanggal membedakan rencana dari hasil terbukti.
Epoch’s current campus estimate: 157 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 157 MW”
Physical-stage observation dated 2026-08-06. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“building 9 is under construction”
Epoch’s dated 2026-08-06 assessment: building 9 is under construction Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“building 9 is under construction”
Epoch estimates AI hardware: Huawei Ascend 910C chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Huawei Ascend 910C chips.”
Epoch dated observation: Land clearing begins, with the east campus being the first of the three.
“Land clearing begins, with the east campus being the first of the three.”
Epoch dated observation: On the north campus, building 5 is structurally complete but not…
“On the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars.”
Foto dari pembaca, terpisah dari media bersumber milik pin. Nilai apa yang Anda makan atau lihat, dan di pin restoran, tandai hidangan langsung pada foto Anda.
Entri pertama selalu merupakan sumber pin. Keyakinan keseluruhan adalah rata-rata tertimbang dari seberapa kuat setiap referensi mendukung waktu mulai dan berakhir yang digunakan di atas; bobot sebuah referensi berkurang setengahnya untuk setiap 180 hari lebih lama dari yang terbaru.
Tanggal yang disimpan adalah perkiraan pelacakan atau penanda lintasan kapasitas, bukan hari pembukaan pasti yang terverifikasi. Status konstruksi mengikuti tanggal lingkup fisik yang disebutkan; tidak ada penyelesaian yang disimpulkan dari target yang telah berlalu.
Construction research 2026-10-24: Epoch’s[1] 2026-08-06 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “building 9 is under construction” Dated observation 2026-08-06; future trajectory rows and modeled costs are distinguished from this physical milestone.
Ada yang kurang atau salah? Sampaikan dengan kata-kata Anda sendiri: tautan yang mendukung pin ini, tanggal mulai atau berakhir yang berbeda beserta alasannya, atau fakta yang kurang atau keliru. AI memeriksanya terhadap sumber pin ini, mencari sumber yang lebih baik, dan menambahkan halaman mana pun yang mendukung Anda. Sumber pin itu sendiri tetap paling diperhitungkan. Gambar yang menampilkan hal lain, atau menampilkannya dengan buruk, juga diperiksa, lalu diturunkan atau diganti.
Judul asli: Huawei Wuhu AI Data Center Buildout
Huawei Wuhu di Wuhu, Anhui, Tiongkok adalah kampus pusat data AI terdepan yang dioperasikan oleh Huawei dengan kapasitas daya sebesar 457 MW dan 221.924 akselerator AI yang setara dengan H100. 0
Observasi Epoch tahun 2026-08-06 mendokumentasikan sisa konstruksi/instalasi fisik untuk pembangunan yang disebutkan ini. Dalam Proses tidak menyelesaikan bangunan yang beroperasi sebelumnya atau kapasitas di masa depan. Jumlah daya dan akselerator tetap merupakan perkiraan Epoch, bukan peringkat yang disertifikasi oleh operator. Biaya modal dolar 2025 yang dimodelkan mencakup perangkat keras komputasi dan bukan merupakan anggaran konstruksi asli sumber.