Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
| Date | Observed status |
|---|---|
| 2023-09-18 | Conversion starts at CTP-01 (Building 1). The data center was formerly owned by Capital One, now leased to CoreWeave. Source: https://www.datacenterdynamics.com/en/news/chirisa-secures-200-million-loa |
| 2024-01-31 | Building 1's second data hall scheduled to come online this month. |
| 2024-04-30 | Building 1 is scheduled to be fully online by this point, so we count the full 27 MW as operational here. |
| 2025-01-22 | Satellite imagery shows Building 1 complete, with Building 2's yard work and early construction visible. Building 3 hasn't started yet, since the old building is still there. |
| 2026-05-20 | Based on satellite imagery, Building 3 has cleared its land and is beginning construction. Building 2 is operational judging from the colored motion artifacts on the cooling tower fans. |
| 2027-06-30 | Buildings 3 is estimated complete by the end of Q1 2027, based on the current PowerHouse schedule. Added another three months to account for commissioning and server installation. |
Epoch AI satellite-imagery notes, in date order. · sumber
Dalam pembangunan
Digital infrastructure: AI data-center campus buildout · Diperiksa 2026-10-30
Hanya tahap yang dilaporkan yang disorot. Angka dan tanggal membedakan rencana dari hasil terbukti.
Epoch’s current campus estimate: 82 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 82 MW”
Physical-stage observation dated 2026-05-20. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Building 3 has cleared its land and is beginning construction.”
Epoch’s dated 2026-05-20 assessment: Building 3 has cleared its land and is beginning construction. Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Building 3 has cleared its land and is beginning construction.”
Epoch estimates AI hardware: Nvidia H100 and Nvidia B200 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Nvidia H100 and Nvidia B200 chips.”
Epoch dated observation: Conversion starts at CTP-01 (Building 1).
“Conversion starts at CTP-01 (Building 1).”
Epoch dated observation: Based on satellite imagery, Building 3 has cleared its land and is…
“Based on satellite imagery, Building 3 has cleared its land and is beginning construction.”
Foto dari pembaca, terpisah dari media bersumber milik pin. Nilai apa yang Anda makan atau lihat, dan di pin restoran, tandai hidangan langsung pada foto Anda.
Entri pertama selalu merupakan sumber pin. Keyakinan keseluruhan adalah rata-rata tertimbang dari seberapa kuat setiap referensi mendukung waktu mulai dan berakhir yang digunakan di atas; bobot sebuah referensi berkurang setengahnya untuk setiap 180 hari lebih lama dari yang terbaru.
Tanggal yang disimpan adalah perkiraan pelacakan atau penanda lintasan kapasitas, bukan hari pembukaan pasti yang terverifikasi. Status konstruksi mengikuti tanggal lingkup fisik yang disebutkan; tidak ada penyelesaian yang disimpulkan dari target yang telah berlalu.
Construction research 2026-10-24: Epoch’s[1] 2026-05-20 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Building 3 has cleared its land and is beginning construction.” Dated observation 2026-05-20; future trajectory rows and modeled costs are distinguished from this physical milestone.
Ada yang kurang atau salah? Sampaikan dengan kata-kata Anda sendiri: tautan yang mendukung pin ini, tanggal mulai atau berakhir yang berbeda beserta alasannya, atau fakta yang kurang atau keliru. AI memeriksanya terhadap sumber pin ini, mencari sumber yang lebih baik, dan menambahkan halaman mana pun yang mendukung Anda. Sumber pin itu sendiri tetap paling diperhitungkan. Gambar yang menampilkan hal lain, atau menampilkannya dengan buruk, juga diperiksa, lalu diturunkan atau diganti.
Judul asli: CoreWeave Chester VA AI Data Center Buildout
Observasi Epoch pada 20-05-2026 mendokumentasikan sisa konstruksi/instalasi fisik untuk pembangunan yang disebutkan ini. Dalam Proses tidak menyelesaikan bangunan yang beroperasi sebelumnya atau kapasitas di masa depan. Jumlah daya dan akselerator tetap merupakan perkiraan Epoch, bukan peringkat yang disertifikasi oleh operator. Biaya modal dolar 2025 yang dimodelkan mencakup perangkat keras komputasi dan bukan merupakan anggaran konstruksi asli sumber.
Pelatihan AI perbatasan hiperskala dan kampus inferensi yang dilacak oleh Epoch AI dengan jejak satelit beranotasi (9 bagian fisik).