Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
| Date | Observed status |
|---|---|
| 2023-08-30 | Building 1, which was first operational in 2021, has increased power capacity by about 75%. This is based on the expansion of the dry cooling array from 4 to 7 columns (seen on [Google Earth](https:// |
| 2025-03-11 | Building 2 now has generators in place, but there is still a crane and construction work present. |
| 2025-06-30 | Building 2 is operational. Based on a [Google Earth image](https://earth.google.com/web/@39.49733738,-119.43113543,1552.05877612a,1467.7067385d,35y,0h,0t,0r/) showing complete building shell, mechanic |
| 2025-09-28 | Building 3 foundation is underway. Building 2 exterior looks totally clean/landscaped. |
| 2026-04-13 | Building 3 has a partially complete shell, electrical and mechanical equipment. Building 4 foundation is underway. |
| 2027-06-30 | Building 3 is estimated to be operational. We estimate the operational date by analogy to the time that Building 1 took to go from a foundation to being operational. The power capacity is based on the |
Epoch AI satellite-imagery notes, in date order. · sumber
Dalam pembangunan
Digital infrastructure: AI data-center campus buildout · Diperiksa 2026-10-30
Hanya tahap yang dilaporkan yang disorot. Angka dan tanggal membedakan rencana dari hasil terbukti.
Epoch’s current campus estimate: 161 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 161 MW”
Physical-stage observation dated 2026-04-13. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Building 4 foundation is underway.”
Epoch’s dated 2026-04-13 assessment: Building 4 foundation is underway. Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Building 4 foundation is underway.”
Epoch estimates AI hardware: Google TPU v5e, Google TPU v4, Google TPU v6e, and Google TPU v5p chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Google TPU v5e, Google TPU v4, Google TPU v6e, and Google TPU v5p chips.”
Epoch dated observation: Building 1, which was first operational in 2021, has increased power…
“Building 1, which was first operational in 2021, has increased power capacity by about 75%.”
Epoch dated observation: Building 3 has a partially complete shell, electrical and mechanical…
“Building 3 has a partially complete shell, electrical and mechanical equipment.”
Foto dari pembaca, terpisah dari media bersumber milik pin. Nilai apa yang Anda makan atau lihat, dan di pin restoran, tandai hidangan langsung pada foto Anda.
Entri pertama selalu merupakan sumber pin. Keyakinan keseluruhan adalah rata-rata tertimbang dari seberapa kuat setiap referensi mendukung waktu mulai dan berakhir yang digunakan di atas; bobot sebuah referensi berkurang setengahnya untuk setiap 180 hari lebih lama dari yang terbaru.
Tanggal yang disimpan adalah perkiraan pelacakan atau penanda lintasan kapasitas, bukan hari pembukaan pasti yang terverifikasi. Status konstruksi mengikuti tanggal lingkup fisik yang disebutkan; tidak ada penyelesaian yang disimpulkan dari target yang telah berlalu.
Construction research 2026-10-24: Epoch’s[1] 2026-04-13 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Building 4 foundation is underway.” Dated observation 2026-04-13; future trajectory rows and modeled costs are distinguished from this physical milestone.
Ada yang kurang atau salah? Sampaikan dengan kata-kata Anda sendiri: tautan yang mendukung pin ini, tanggal mulai atau berakhir yang berbeda beserta alasannya, atau fakta yang kurang atau keliru. AI memeriksanya terhadap sumber pin ini, mencari sumber yang lebih baik, dan menambahkan halaman mana pun yang mendukung Anda. Sumber pin itu sendiri tetap paling diperhitungkan. Gambar yang menampilkan hal lain, atau menampilkannya dengan buruk, juga diperiksa, lalu diturunkan atau diganti.
Judul asli: Google Storey County AI Data Center Buildout
Observasi Epoch pada 13-04-2026 mendokumentasikan sisa konstruksi/instalasi fisik untuk pembangunan yang disebutkan ini. Dalam Proses tidak menyelesaikan bangunan yang beroperasi sebelumnya atau kapasitas di masa depan. Jumlah daya dan akselerator tetap merupakan perkiraan Epoch, bukan peringkat yang disertifikasi oleh operator. Biaya modal dolar 2025 yang dimodelkan mencakup perangkat keras komputasi dan bukan merupakan anggaran konstruksi asli sumber.
Kampus pelatihan dan inferensi AI perbatasan hiperskala yang dilacak oleh Epoch AI dengan jejak satelit beranotasi (16 bagian fisik).