Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
| Date | Observed status |
|---|---|
| 2021-07-01 | Land clearing begins. [Talen Energy](https://www.datacenterdynamics.com/en/news/talen-energy-to-build-300mw-nuclear-powered-cryptomining-facility-and-data-center-in-us/) reported on July 12, 2021 that |
| 2023-01-17 | [Cumulus](https://www.prnewswire.com/news-releases/cumulus-data-completes-key-milestones-in-construction-of-its-flagship-zero-carbon-susquehanna-data-center-campus-301722751.html) completes a 48 MW, 3 |
| 2024-03-04 | [AWS](https://www.sec.gov/Archives/edgar/data/1622536/000162828025023501/tln-20250331.htm) acquires the Cumulus/Talen building campus for $650M. |
| 2024-06-01 | Building 1 fit out and related construction begins under Amazon, based on the [Susquehanna River Basin Commission](https://www.srbc.gov/waav/search/GetPending?documentType=Application&isABRe=false&pro |
| 2025-09-09 | Building 1 operational estimate. According to [Google Earth Satellite Imagery](https://earth.google.com/web/search/Berwick,+PA/@41.08459175,-76.14321499,203.05778839a,756.59305105d,35y,0h,0t,0r/data=C |
| 2026-01-07 | Building 2 operational estimate. This is based on the progress visible in the September 2025 image. [The DEP](https://www.pacodeandbulletin.gov/secure/pabulletin/data/vol56/56-4/56-4.pdf) also issues |
| 2026-03-12 | [The SRBC](https://www.srbc.gov/waav/Search/getdocket?documenttype=Approval&isabre=False&projectnumber=20260301) increases approved water use from 0.060 MGD to 0.129 MGD. This supports that some expan |
| 2026-05-05 | Buildings 1 and 2 visibly complete and operational. Building 3 appears complete and may be commissioning, but it's likely not operational yet given the immediate surrounding construction work. Several |
| 2026-08-01 | Building 3 expected to come online sometime around August 2026, since in the May satellite image it appeared structurally complete with minimal construction surrounding it. Basing MW estimate using Bu |
| 2027-08-01 | Building 4 expected to come online around August 2027, judging from prior satellite imagery. Modeled at twice Building 2's capacity because Building 4 is approximately twice its size. |
Epoch AI satellite-imagery notes, in date order. · sumber
Dalam pembangunan
Digital infrastructure: AI data-center campus buildout · Diperiksa 2026-10-30
Hanya tahap yang dilaporkan yang disorot. Angka dan tanggal membedakan rencana dari hasil terbukti.
Epoch’s current campus estimate: 108 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 108 MW”
Physical-stage observation dated 2026-05-05. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Several additional building shells and pads are still in construction”
Epoch’s dated 2026-05-05 assessment: Several additional building shells and pads are still in construction Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Several additional building shells and pads are still in construction”
Epoch estimates AI hardware: Amazon Trainium2 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Amazon Trainium2 chips.”
Epoch dated observation: Land clearing begins.
“Land clearing begins.”
Epoch dated observation: Buildings 1 and 2 visibly complete and operational.
“Buildings 1 and 2 visibly complete and operational.”
Epoch assessment: Building 3 expected to come online sometime around August 2026, since in the…
“Building 3 expected to come online sometime around August 2026, since in the May satellite image it appeared structurally complete with minimal construction surrounding it.”
Foto dari pembaca, terpisah dari media bersumber milik pin. Nilai apa yang Anda makan atau lihat, dan di pin restoran, tandai hidangan langsung pada foto Anda.
Entri pertama selalu merupakan sumber pin. Keyakinan keseluruhan adalah rata-rata tertimbang dari seberapa kuat setiap referensi mendukung waktu mulai dan berakhir yang digunakan di atas; bobot sebuah referensi berkurang setengahnya untuk setiap 180 hari lebih lama dari yang terbaru.
Tanggal yang disimpan adalah perkiraan pelacakan atau penanda lintasan kapasitas, bukan hari pembukaan pasti yang terverifikasi. Status konstruksi mengikuti tanggal lingkup fisik yang disebutkan; tidak ada penyelesaian yang disimpulkan dari target yang telah berlalu.
Construction research 2026-10-24: Epoch’s[1] 2026-05-05 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Several additional building shells and pads are still in construction” Dated observation 2026-05-05; future trajectory rows and modeled costs are distinguished from this physical milestone.
Ada yang kurang atau salah? Sampaikan dengan kata-kata Anda sendiri: tautan yang mendukung pin ini, tanggal mulai atau berakhir yang berbeda beserta alasannya, atau fakta yang kurang atau keliru. AI memeriksanya terhadap sumber pin ini, mencari sumber yang lebih baik, dan menambahkan halaman mana pun yang mendukung Anda. Sumber pin itu sendiri tetap paling diperhitungkan. Gambar yang menampilkan hal lain, atau menampilkannya dengan buruk, juga diperiksa, lalu diturunkan atau diganti.
Judul asli: AWS Berwick AI Data Center Buildout
Observasi Epoch pada 05-05-2026 mendokumentasikan sisa konstruksi/instalasi fisik untuk pembangunan yang disebutkan ini. Dalam Proses tidak menyelesaikan bangunan yang beroperasi sebelumnya atau kapasitas di masa depan. Jumlah daya dan akselerator tetap merupakan perkiraan Epoch, bukan peringkat yang disertifikasi oleh operator. Biaya modal dolar 2025 yang dimodelkan mencakup perangkat keras komputasi dan bukan merupakan anggaran konstruksi asli sumber.
Pelatihan AI perbatasan hiperskala dan kampus inferensi yang dilacak oleh Epoch AI dengan jejak satelit beranotasi (12 bagian fisik).