Pin ini mengikuti berita: pin ini menampilkan apa yang diketahui saat ini, dan di sini ada apa yang berubah serta penyebabnya.
Dieditoleh @ThePinGang
Sebelumnya
2027. The current operator project page identifies construction underway and expected customer supply in 2027.
Construction is verified; the completion date remains an estimate. The timeline marker represents the published target year/month, not a confirmed opening day.
LG&E/KU’s current Mill Creek 5 page states a 645 MW nameplate rating, $902 million cost, construction underway and estimated completion in 2027. Its 2024 groundbreaking release used 640 MW; the current page is used for the primary output rating. EIA’s separate 740 MW figure is retained as inventory context, not extra generating capacity.
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Operator source page; original image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Operator source page; original image.
Dieditoleh @ThePinGang
Dieditoleh @ThePinGang
Sebelumnya
Sebelumnya
LG&E/KU’s current Mill Creek 5 page states a 645 MW nameplate rating, $902 million cost, construction underway and estimated completion in 2027. Its 2024 groundbreaking release used 640 MW; the current page is used for the primary output rating. EIA’s separate 740 MW figure is retained as inventory context, not extra generating capacity.
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Operator source page; original image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Operator source page; original image.
Dieditoleh @ThePinGang
Sebelumnya
LG&E/KU’s current Mill Creek 5 page states a 645 MW nameplate rating, $902 million cost, construction underway and estimated completion in 2027. Its 2024 groundbreaking release used 640 MW; the current page is used for the primary output rating. EIA’s separate 740 MW figure is retained as inventory context, not extra generating capacity.
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Operator source page; original image.
Dieditoleh @ThePinGang
Sebelumnya
LG&E/KU’s current Mill Creek 5 page states a 645 MW nameplate rating, $902 million cost, construction underway and estimated completion in 2027. Its 2024 groundbreaking release used 640 MW; the current page is used for the primary output rating. EIA’s separate 740 MW figure is retained as inventory context, not extra generating capacity.
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Dieditoleh @ThePinGang
Sebelumnya
Sebelumnya
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels.
EIA August 2026 generator inventory, plant ID 1364: Mill Creek (KY), Jefferson County, KY. Included 1 new/recent generating units with a summed nameplate rating of 740 MW.
EIA reports operation at month/year precision. The date is the last day of the earliest reported operation month/year, an estimated display boundary, not an exact opening day. Different units may have later dates. Future dates are operator-reported plans, not guarantees.
Coordinates are the EIA-reported plant point, not a verified entrance. New units at existing plants are included; the total excludes older units and battery/pumped storage. Capacity is a power rating, not annual energy output. Status was reported in August and may have changed since.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Ini foto pembaca, terpisah dari media pin yang bersumber.
Entri pertama selalu merupakan sumber pin. Keyakinan keseluruhan adalah rata-rata tertimbang dari seberapa kuat setiap referensi mendukung waktu mulai dan berakhir yang digunakan di atas; bobot sebuah referensi berkurang setengahnya untuk setiap 180 hari lebih lama dari yang terbaru.
Target yang dipublikasikan: 2027. Konstruksi terdokumentasi, tetapi tonggak penyelesaian/operasi di masa depan ini hanyalah perkiraan. Tanggalnya adalah penanda lini masa akhir tahun/bulan dan bukan hari pembukaan yang terkonfirmasi. Sumber: https://lge-ku.com[2][3]/mc5
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.[1]
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s[1] August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Ada yang kurang atau salah? Sampaikan dengan kata-kata Anda sendiri: tautan yang mendukung pin ini, tanggal mulai atau berakhir yang berbeda beserta alasannya, atau fakta yang kurang atau keliru. AI memeriksanya terhadap sumber pin ini, mencari sumber yang lebih baik, dan menambahkan halaman mana pun yang mendukung Anda. Sumber pin itu sendiri tetap paling diperhitungkan. Gambar yang menampilkan hal lain, atau menampilkannya dengan buruk, juga diperiksa, lalu diturunkan atau diganti.
Judul asli: Mill Creek 5 — estimated target 2027
2027. Halaman proyek operator saat ini menyebutkan konstruksi sedang berjalan dan pasokan ke pelanggan diperkirakan pada 2027.[2]
Konstruksi telah terverifikasi; tanggal penyelesaian masih berupa perkiraan. Penanda lini masa mewakili tahun/bulan target yang dipublikasikan, bukan hari pembukaan yang terkonfirmasi.
Halaman Mill Creek 5 LG&E/KU saat ini menyebut peringkat nameplate 645 MW, biaya 902 juta dolar, konstruksi sedang berjalan, dan perkiraan penyelesaian pada 2027. Rilis peletakan batu pertama 2024 menggunakan 640 MW; halaman saat ini digunakan untuk peringkat keluaran utama. Angka 740 MW EIA yang terpisah dipertahankan sebagai konteks inventaris, bukan kapasitas pembangkitan tambahan.[2][3]
Biaya khusus proyek yang dipublikasikan untuk Mill Creek 5: USD 9.02e+08. Dasar: Perkiraan modal/biaya konstruksi khusus proyek yang dipublikasikan. Peringkat proyek pembangkit listrik yang dipublikasikan untuk Mill Creek 5: 645 MW. Dasar: Halaman operator saat ini: kapasitas nameplate 645 MW.[2]
LG&E dan KU memulai peletakan batu pertama Mill Creek 5 pada 13 November 2024 dan menggambarkan unit siklus gabungan gas alam 640 MW yang diperkirakan pada 2027. Catatan konstruksi EIA Agustus 2026 secara independen mendukung pekerjaan yang sedang berlangsung. Peringkat proyek 640 MW operator dan peringkat nameplate generator EIA menggunakan angka yang berbeda; kedua label dipertahankan. Peletakan batu pertama pada 13 November 2024 memverifikasi konstruksi fisik.[3]
Hanya proyek dengan konstruksi fisik, komisioning, atau pembukaan 2025–2026 yang terdokumentasi serta biaya dan keluaran listrik khusus proyek yang dipublikasikan yang dipertahankan. Biaya memakai cakupan dan mata uang yang dipublikasikan; tidak ada perkiraan tolok ukur atau konversi mata uang. MW adalah kapasitas daya, bukan produksi listrik tahunan. Energi tahunan yang diharapkan, bila ada, merupakan perkiraan. Titik peta adalah lokasi pembangkit/proyek yang dilaporkan dan dapat berupa perkiraan. Tampilan inventaris yang cocok dan usulan perluasan yang dikecualikan bukan kapasitas yang dapat dijumlahkan.
Rendering operator untuk Mill Creek 5. Ini adalah ilustrasi unit yang direncanakan, bukan foto pembangkit yang telah selesai. Kredit: LG&E and KU; seniman tidak disebutkan di halaman sumber. Halaman sumber; gambar asli operator.
Upacara peletakan batu pertama Mill Creek 5, 13 November 2024, seperti dipublikasikan dalam rilis operator. Kredit: LG&E and KU; fotografer tidak disebutkan di halaman sumber. Halaman sumber; gambar asli operator.
Rendering operator untuk Mill Creek 5. Ini adalah ilustrasi unit yang direncanakan, bukan foto pembangkit yang telah selesai. Kredit: LG&E and KU; seniman tidak disebutkan di halaman sumber. Halaman sumber operator; gambar asli.
Upacara peletakan batu pertama Mill Creek 5, 13 November 2024, seperti dipublikasikan dalam rilis operator. Kredit: LG&E and KU; fotografer tidak disebutkan di halaman sumber. Halaman sumber operator; gambar asli.
Lokasi konstruksi Mill Creek 5, dari galeri proyek LG&E dan KU. Tanggal pengambilan tidak disebutkan secara terpisah. Kredit: LG&E and KU; fotografer tidak disebutkan. Sumber dan galeri; media asli.
Lokasi konstruksi Mill Creek 5, dari galeri proyek LG&E dan KU. Tanggal pengambilan tidak disebutkan secara terpisah. Kredit: LG&E and KU; fotografer tidak disebutkan. Sumber dan galeri; media asli.