Energy: battery storage · Verificato il 2026-10-30
È evidenziata solo la fase riportata. Cifre e date distinguono i piani dai risultati dimostrati.
250 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"Batesville 138kV Substation","summerNetMW":250.0”
2027-09-30; requested date only, not an achieved opening.
“"projectNumber":"J2581","queueDate":"2022-09-15T04:00:00+00:00","inService":"2027-09-30T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":"Not Started"”
Battery Storage; Batesville 138kV Substation.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J2581","queueDate":"2022-09-15T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J2581","queueDate":"2022-09-15T04:00:00+00:00","inService":"2027-09-30T04:00:00+00:00"”
Questo pin segue le notizie: mostra ciò che si sa ora, e qui trovi cosa è cambiato e da dove.
Modificatodi @ThePinGang
MISO regional transmission interconnection development of the Batesville Energy Storage Center in Ripley County, Indiana. SupplyingJ2581 is a 250 MW / 1,000 MWh of utility-scale battery energy storage, the facility interfaces with the Batesville 138 kV substation to provide rapid frequency response, grid inertia, and capacity firming across southeastern Indiana.battery storage interconnection request in Ripley, IN. The grid operator lists its queue status as Active. The requested in-service date is 2027-09-30; this is a planning date.
Batesville Energy Storage LLC submitted interconnection filings for the Batesville Energy Storage CenterJ2581 is a 250 MW battery storage interconnection request in Ripley County, Indiana. Deploys 250 MW / 1,000 MWh of utility-scale four-hour duration lithium-ion battery storage. Represents an estimated 250 million USD private clean energy infrastructure investment in southeastern Indiana. Interconnects to the Batesville 138 kV substation within the MISO transmission footprint. Provides essential rapid frequency regulation, system inertia, and regional capacity firming. Timeline: planned project targeting commercial operation in September 2027 (estimated) under MISO interconnection queue and state regulatory schedules.Ripley, IN. The grid operator lists its queue status as Active. The requested in-service date is 2027-09-30; this is a planning date. The point of interconnection is Batesville 138kV Substation. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
Modificatodi @ThePinGang
… frequency regulation, system inertia, and regional capacity firming. Timeline: planned project targeting commercial operation in September 2027 (estimated) under MISO interconnection queue and state regulatory schedules.
Modificatodi @ThePinGang
Foto dei lettori, separate dai media con fonti del pin. Valuta ciò che hai mangiato o visto e, su un pin di ristorante, tagga i piatti direttamente sulla tua foto.
La prima voce è sempre la fonte del pin. L’affidabilità complessiva è una media ponderata di quanto ogni fonte conferma gli orari di inizio e fine indicati sopra; una fonte conta la metà per ogni 180 giorni in più rispetto alla più recente.
Manca qualcosa o c’è un errore? Dillo con parole tue: un link che conferma questo pin, una data di inizio o fine diversa e perché, o un fatto che manca o è sbagliato. L’IA lo confronta con le fonti del pin, ne cerca di migliori e aggiunge qualsiasi pagina ti dia ragione. Le fonti del pin contano comunque di più. Anche un’immagine che mostra altro, o lo mostra male, viene esaminata e spostata in basso o sostituita.
Titolo originale: Batesville: 250 MW Battery Interconnection Request J2581
Power storage250 MW · J2581: 250 MW requested battery storage. Queue status: Active. Requested date: 2027-09-30. Not current measured generation; No annual energy or battery MWh inferred. · source