Energy: battery storage · Verificato il 2026-10-30
È evidenziata solo la fase riportata. Cifre e date distinguono i piani dai risultati dimostrati.
100 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"LAGRANGE","summerNetMW":100.0”
2027-06-30; requested date only, not an achieved opening.
“"projectNumber":"S1108","queueDate":"2025-07-18T04:00:00+00:00","inService":"2027-06-30T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":""”
Battery Storage; LAGRANGE.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"S1108","queueDate":"2025-07-18T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"S1108","queueDate":"2025-07-18T04:00:00+00:00","inService":"2027-06-30T04:00:00+00:00"”
Questo pin segue le notizie: mostra ciò che si sa ora, e qui trovi cosa è cambiato e da dove.
Modificatodi @ThePinGang
NIPSCO transmission-interconnected development of the LaGrange Clean Energy Storage Complex in LaGrange County, Indiana. DeliveringS1108 is a 100 MW / 400 MWh of utility-scale battery storage, the system interfaces with northern Indiana transmission corridors to balance variable wind and solar energy feeds across regional rural electric networks.battery storage interconnection request in LaGrange, IN. The grid operator lists its queue status as Active. The requested in-service date is 2027-06-30; this is a planning date.
NIPSCO progressed transmission interconnection filings for the LaGrange Clean Energy Storage ComplexS1108 is a 100 MW battery storage interconnection request in LaGrange County, Indiana. Supplies 100 MW / 400 MWh of advanced lithium-ion battery energy storage. Represents a 120 million USD clean energy capital expenditure in northern Indiana. Interfaces directly with regional transmission corridors along US Route 20. Balances variable wind and solar feeds across regional rural electric networks. Timeline: planned project targeting commercial operation in June 2027 (estimated) under MISO interconnection queue and state regulatory schedules.LaGrange, IN. The grid operator lists its queue status as Active. The requested in-service date is 2027-06-30; this is a planning date. The point of interconnection is LAGRANGE. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
Modificatodi @ThePinGang
… and solar feeds across regional rural electric networks. Timeline: planned project targeting commercial operation in June 2027 (estimated) under MISO interconnection queue and state regulatory schedules.
Foto dei lettori, separate dai media con fonti del pin. Valuta ciò che hai mangiato o visto e, su un pin di ristorante, tagga i piatti direttamente sulla tua foto.
La prima voce è sempre la fonte del pin. L’affidabilità complessiva è una media ponderata di quanto ogni fonte conferma gli orari di inizio e fine indicati sopra; una fonte conta la metà per ogni 180 giorni in più rispetto alla più recente.
Manca qualcosa o c’è un errore? Dillo con parole tue: un link che conferma questo pin, una data di inizio o fine diversa e perché, o un fatto che manca o è sbagliato. L’IA lo confronta con le fonti del pin, ne cerca di migliori e aggiunge qualsiasi pagina ti dia ragione. Le fonti del pin contano comunque di più. Anche un’immagine che mostra altro, o lo mostra male, viene esaminata e spostata in basso o sostituita.
Titolo originale: LaGrange Energy Storage Complex: 100 MW Battery Interconnection Request S1108
Power storage100 MW · S1108: 100 MW requested battery storage. Queue status: Active. Requested date: 2027-06-30. Not current measured generation; No annual energy or battery MWh inferred. · source