Annunciata
Energy: battery storage · Verificato il 2026-10-30
È evidenziata solo la fase riportata. Cifre e date distinguono i piani dai risultati dimostrati.
100 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"LOOSE CREEK","summerNetMW":100.0”
2027-12-03; requested date only, not an achieved opening.
“"projectNumber":"J3736","queueDate":"2024-04-17T04:00:00+00:00","inService":"2027-12-03T05:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":""”
Battery Storage; LOOSE CREEK.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J3736","queueDate":"2024-04-17T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J3736","queueDate":"2024-04-17T04:00:00+00:00","inService":"2027-12-03T05:00:00+00:00"”
Questo pin segue le notizie: mostra ciò che si sa ora, e qui trovi cosa è cambiato e da dove.
Modificatodi @ThePinGang
MISO regional transmission interconnection development of the Loose Creek Clean Energy Storage Center in Osage County, Missouri. SupplyingJ3736 is a 100 MW / 400 MWh of battery energy storage connected to the 161 kV central Missouri transmission network, the project provides fast-ramping reserve power and congestion relief near Jefferson City.battery storage interconnection request in Osage, MO. The grid operator lists its queue status as Active. The requested in-service date is 2027-12-03; this is a planning date.
Ameren Missouri submitted transmission interconnection petitions for the Loose Creek Clean Energy Storage Center in Osage County, Missouri. ProvidesJ3736 is a 100 MW / 400 MWh of modular lithium-ion battery energy storage capacity. Represents an estimated 120 million USD clean infrastructure investment in central Missouri. Connects to the 161 kV transmission network along the US Highway 50 corridor east of Jefferson City. Supplies fast-responding spinning reserve and transmission congestion relief across central Missouri. Timeline: planned utility-scale battery storage project targeting commercial operation in December 2027 (estimated) per MISO generator interconnection queue and Missouri PSC filings.battery storage interconnection request in Osage, MO. The grid operator lists its queue status as Active. The requested in-service date is 2027-12-03; this is a planning date. The point of interconnection is LOOSE CREEK. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
Foto dei lettori, separate dai media con fonti del pin. Valuta ciò che hai mangiato o visto e, su un pin di ristorante, tagga i piatti direttamente sulla tua foto.
La prima voce è sempre la fonte del pin. L’affidabilità complessiva è una media ponderata di quanto ogni fonte conferma gli orari di inizio e fine indicati sopra; una fonte conta la metà per ogni 180 giorni in più rispetto alla più recente.
Manca qualcosa o c’è un errore? Dillo con parole tue: un link che conferma questo pin, una data di inizio o fine diversa e perché, o un fatto che manca o è sbagliato. L’IA lo confronta con le fonti del pin, ne cerca di migliori e aggiunge qualsiasi pagina ti dia ragione. Le fonti del pin contano comunque di più. Anche un’immagine che mostra altro, o lo mostra male, viene esaminata e spostata in basso o sostituita.
Titolo originale: Loose Creek: 100 MW Battery Interconnection Request J3736
Power storage100 MW · J3736: 100 MW requested battery storage. Queue status: Active. Requested date: 2027-12-03. Not current measured generation; No annual energy or battery MWh inferred. · source