| Date | Observed status |
|---|---|
| 2024-04-20 | Building 1 is operational. Based on ~7 months since roof being completed, and cooling towers being installed sometime within that period. Building 2 roof is complete. |
| 2024-09-13 | Building 2 is operational. Google Earth imagery shows 6 cooling towers installed as of 2024-04-20, and a final 7th unit appeared as of 2024-09-13, with minimal construction around the building. Buildi |
| 2025-06-01 | Building 3 is operational, based on all cooling units and tanks installed, minimal construction work around the building. Building 4 still has some work around the cooling towers. Work is underway on |
| 2025-10-14 | Building 4 is operational, based on all cooling units and tanks installed, minimal construction work around the building. Building 5 roof is half complete. About half of the backup generators are in p |
| 2026-01-18 | Water vapor from cooling towers is present across Building 1-4, confirming their operation. Building 5 roof is still incomplete, but most backup generators and 5 cooling towers have been installed. |
| 2026-03-12 | Building 5 has more cooling towers installed but not complete, and the roof is almost complete. |
| 2026-05-18 | Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building. Based on that, we estimate 3 more months until operational. |
Epoch AI satellite-imagery notes, in date order. · fonte
In costruzione
Digital infrastructure: AI data-center campus buildout · Verificato il 2026-10-30
È evidenziata solo la fase riportata. Cifre e date distinguono i piani dai risultati dimostrati.
Epoch’s current campus estimate: 333 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 333 MW”
Physical-stage observation dated 2026-05-18. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“there is still light work around the building”
Epoch’s dated 2026-05-18 assessment: there is still light work around the building Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“there is still light work around the building”
Epoch estimates AI hardware: Google TPU v5e, Google TPU v5p, and Google TPU v6e chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Google TPU v5e, Google TPU v5p, and Google TPU v6e chips.”
Epoch dated observation: Building 1 is operational.
“Building 1 is operational.”
Epoch dated observation: Building 5 has all cooling towers installed, and all other components…
“Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building.”
Foto dei lettori, separate dai media con fonti del pin. Valuta ciò che hai mangiato o visto e, su un pin di ristorante, tagga i piatti direttamente sulla tua foto.
La prima voce è sempre la fonte del pin. L’affidabilità complessiva è una media ponderata di quanto ogni fonte conferma gli orari di inizio e fine indicati sopra; una fonte conta la metà per ogni 180 giorni in più rispetto alla più recente.
La data salvata è un indicatore di tracciamento stimato o di traiettoria di capacità, non un giorno di apertura esatto verificato. Lo stato di costruzione segue l'ambito fisico datato citato; nessun completamento viene dedotto dagli obiettivi trascorsi.
Construction research 2026-10-24: Epoch’s[1] 2026-05-18 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “there is still light work around the building” Dated observation 2026-05-18; future trajectory rows and modeled costs are distinguished from this physical milestone.
Manca qualcosa o c’è un errore? Dillo con parole tue: un link che conferma questo pin, una data di inizio o fine diversa e perché, o un fatto che manca o è sbagliato. L’IA lo confronta con le fonti del pin, ne cerca di migliori e aggiunge qualsiasi pagina ti dia ragione. Le fonti del pin contano comunque di più. Anche un’immagine che mostra altro, o lo mostra male, viene esaminata e spostata in basso o sostituita.
Titolo originale: Google New Albany AI Data Center Buildout
Google New Albany a New Albany, Ohio, Stati Uniti è un campus di data center AI di frontiera gestito da Google/Google DeepMind che raggiunge 333 MW di capacità di potenza e 323.901 acceleratori AI equivalenti a H100. 0
L'osservazione di Epoch del 18-05-2026 documenta la restante costruzione/installazione fisica per questo edificio denominato. In Progress non completa gli edifici operativi precedenti o la capacità futura. I conteggi di potenza e acceleratore rimangono stime epocali, non una valutazione certificata dall'operatore. I costi di capitale modellati in dollari del 2025 includono l'hardware di elaborazione e non rappresentano un budget di costruzione nativo della fonte.