La prima voce è sempre la fonte del pin. L’affidabilità complessiva è una media ponderata di quanto ogni fonte conferma gli orari di inizio e fine indicati sopra; una fonte conta la metà per ogni 180 giorni in più rispetto alla più recente.
L'inizio è il disboscamento osservato da Epoch[3][6] (27-09-2025). La fine è la piena operatività prevista di Epoch (31-12-2028), una stima, non una data per lo sviluppatore. L'inizio esistente della spilla (28-12-2028) è la proiezione, non una data rivoluzionaria.
Cited in the project timeline.[1]
Construction research 2026-10-24: Epoch’s[1][6] 2026-03-23 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Steel framing and roofing is underway for Building 1.” Dated observation 2026-03-23; future trajectory rows and modeled costs are distinguished from this physical milestone.
Photo caption and image of Burlington construction May 4, 2026[1]
| 2026-01-04 | Inizia la costruzione di piccole sezioni delle fondamenta dell'edificio e lo sgombero del terreno sembra essere in gran parte terminato |
|---|
| 2026-03-23 | Sono in corso i lavori di struttura in acciaio e copertura dell'edificio 1. |
|---|
| 2028-12-31 | Tutti gli edifici sono terminati, il sito è pienamente operativo. Il nostro ragionamento è che finora gli esempi impiegano una media di 2-2,5 anni per passare dal disboscamento a 1 GW. Ciò suggerisce… |
|---|
Note sulle immagini satellitari di Epoch AI, in ordine di data. · fonte
548,950 sq ft, single story, four data halls
“will comprise a single-story 548,950 square foot (51,000 sqm) data center with four data halls.”
1.2 GW planned
“build and operate the previously announced 1.2 GW Stargate data center in Milam County, Texas.”
15 October (2026) / Q4 2028
“All buildings finished, site is fully operational.”
Building 1 steel and roofing; no building confirmed operational
“Steel framing and roofing is underway for Building 1.”
Land clearing begins (Epoch satellite observation)
“Land clearing begins for the site”
Building foundation construction begins
“Small sections of building foundation construction begins, and land clearing appears to be mostly finished”
SB Energy to build and operate the 1.2 GW site; OpenAI and SoftBank invest $1B in SB Energy
“SB Energy will provide the project's powered infrastructure, while SoftBank and OpenAI invest $1 billion in the company to support its growth”
Steel framing and roofing underway for Building 1
“Steel framing and roofing is underway for Building 1.”
TDLR filing for Freebird Phase 1: 548,950 sq ft, four data halls, about $470 million
“The filing discloses the estimated cost of the project at $470 million, with a project completion date of 15 October.”
Phase 1 completion date in TDLR filing (no confirmation of completion published)
“with a project completion date of 15 October.”
Full site fully operational (Epoch projection)
“All buildings finished, site is fully operational.”
Manca qualcosa o c’è un errore? Dillo con parole tue: un link che conferma questo pin, una data di inizio o fine diversa e perché, o un fatto che manca o è sbagliato. L’IA lo confronta con le fonti del pin, ne cerca di migliori e aggiunge qualsiasi pagina ti dia ragione. Le fonti del pin contano comunque di più. Anche un’immagine che mostra altro, o lo mostra male, viene esaminata e spostata in basso o sostituita.
Titolo originale: OpenAI Stargate Milam AI Data Center Buildout
Il campus Stargate Milam di OpenAI vicino a Burlington, in Texas, è un data center pianificato da 1,2 GW che SB Energy di SoftBank sta costruendo e gestisce. Le immagini satellitari mostrano strutture e coperture in acciaio sull'Edificio 1 entro marzo 2026, e un documento statale per la Fase 1 elenca 548.950 piedi quadrati e circa 470 milioni di dollari. Epoch AI prevede la piena operatività entro la fine del 2028. Nessun edificio è ancora confermato operativo.
L'osservazione di Epoch del 23-03-2026 documenta la restante costruzione/installazione fisica per questo edificio denominato. In Progress non completa gli edifici operativi precedenti o la capacità futura. I conteggi di potenza e acceleratore rimangono stime epocali, non una valutazione certificata dall'operatore. I costi di capitale modellati in dollari del 2025 includono l'hardware di elaborazione e non rappresentano un budget di costruzione nativo della fonte.