| Date | Observed status |
|---|---|
| 2023-01-01 | Land clearing begins, with the east campus being the first of the three. Land clearing begins for the other two campuses months after. |
| 2025-01-01 | The first building is operational. On the north campus, building 4 is operational assuming a 3-month fit-out post structural completion. |
| 2025-03-01 | Three buildings are operational. On the west campus, building 1 is operational, and on the east campus, building 7 is operational. The second building on the east campus has installed generators, but |
| 2025-11-01 | Four buildings are operational. On the west campus, building 2 is operational assuming a 3-month fit-out post structural completion. |
| 2026-01-24 | Four buildings are operational in total. A fifth building, building 5 on the north campus, is finishing installing roofside cooling. Another building on the east campus is complete but does not have s |
| 2026-06-01 | Four buildings are operational. On the north campus, building 5 is nearing structural completion but still has roofing and cooling remaining. |
| 2026-08-06 | On the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars. Building 6, a much larger building across the pond, should finish construction in |
| 2026-11-01 | Five buildings are operational. On the north campus, building 5 is operational assuming a 3-month fit-out post structural completion. |
| 2026-12-31 | Six buildings are operational. On the north campus, building 6, the larger building, is operational assuming a 3-month fit-out if it is structurally complete in September. We assume Building 6 is abou |
| 2027-12-01 | All eight AI buildings are operational. Buildings 3 and 9 are assumed to be 1.25x the power and compute of buildings 1 and 7 based on the sizing of the backup generator enclosures; building 8 is exclu |
Epoch AI satellite-imagery notes, in date order. · fonte
In costruzione
Digital infrastructure: AI data-center campus buildout · Verificato il 2026-10-30
È evidenziata solo la fase riportata. Cifre e date distinguono i piani dai risultati dimostrati.
Epoch’s current campus estimate: 157 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 157 MW”
Physical-stage observation dated 2026-08-06. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“building 9 is under construction”
Epoch’s dated 2026-08-06 assessment: building 9 is under construction Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“building 9 is under construction”
Epoch estimates AI hardware: Huawei Ascend 910C chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Huawei Ascend 910C chips.”
Epoch dated observation: Land clearing begins, with the east campus being the first of the three.
“Land clearing begins, with the east campus being the first of the three.”
Epoch dated observation: On the north campus, building 5 is structurally complete but not…
“On the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars.”
Foto dei lettori, separate dai media con fonti del pin. Valuta ciò che hai mangiato o visto e, su un pin di ristorante, tagga i piatti direttamente sulla tua foto.
La prima voce è sempre la fonte del pin. L’affidabilità complessiva è una media ponderata di quanto ogni fonte conferma gli orari di inizio e fine indicati sopra; una fonte conta la metà per ogni 180 giorni in più rispetto alla più recente.
La data salvata è un indicatore di tracciamento stimato o di traiettoria di capacità, non un giorno di apertura esatto verificato. Lo stato di costruzione segue l'ambito fisico datato citato; nessun completamento viene dedotto dagli obiettivi trascorsi.
Construction research 2026-10-24: Epoch’s[1] 2026-08-06 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “building 9 is under construction” Dated observation 2026-08-06; future trajectory rows and modeled costs are distinguished from this physical milestone.
Manca qualcosa o c’è un errore? Dillo con parole tue: un link che conferma questo pin, una data di inizio o fine diversa e perché, o un fatto che manca o è sbagliato. L’IA lo confronta con le fonti del pin, ne cerca di migliori e aggiunge qualsiasi pagina ti dia ragione. Le fonti del pin contano comunque di più. Anche un’immagine che mostra altro, o lo mostra male, viene esaminata e spostata in basso o sostituita.
Titolo originale: Huawei Wuhu AI Data Center Buildout
Huawei Wuhu a Wuhu, Anhui, Cina è un campus di data center AI di frontiera gestito da Huawei che raggiunge 457 MW di capacità energetica e 221.924 acceleratori AI equivalenti a H100. 0
L'osservazione di Epoch del 06-08-2026 documenta la restante costruzione/installazione fisica per questo edificio denominato. In Progress non completa gli edifici operativi precedenti o la capacità futura. I conteggi di potenza e acceleratore rimangono stime epocali, non una valutazione certificata dall'operatore. I costi di capitale modellati in dollari del 2025 includono l'hardware di elaborazione e non rappresentano un budget di costruzione nativo della fonte.