RWE Q1 2021 publishes anticipated project investment of approximately £3 billion for Sofia, including the grid connection that must be sold after completion. Published generating capacity is 1,400 MW. This is the original investment-decision estimate, not a newly calculated 2026 budget.
RWE Q1 2021 publishes anticipated project investment of approximately £3 billion for Sofia, including the grid connection that must be sold after completion. Published generating capacity is 1,400 MW. This is the original investment-decision estimate, not a newly calculated 2026 budget. Sofia offshore wind farm: 1400 MW generating project rating. Operator-reported electric generating capacity; not annual energy production
RWE June 11, 2026 confirms installation of all 100 × 14 MW turbines, final turbine installation June 10. Construction/commissioning continues; the announcement does not prove full commercial operation.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
編集@ThePinGang による
読者の写真で、出典付きのピンのメディアとは別に表示されます。
最初の項目は常にピンの出典です。全体の確度は、各資料が上記の開始・終了時刻をどれだけ強く裏付けているかの加重平均です。最新の資料より180日古くなるごとに、重みは半分になります。
文書で確認された物理的なマイルストーン、または日付付きの進捗・報告の目安。期間末の日付は報告された月・四半期のみを表し、正確な稼働日を作り出すものではない。情報源の推定値はそのように表示され、確定した将来の開業日としては扱わない。
Steady development at the Sofia array, with over 80 turbines now installed (May 2026). Official project gallery photograph; the date is the operator’s gallery label.[1]
RWE[4] Q1 2021 publishes anticipated project investment of approximately £3 billion for Sofia, including the grid connection that must be sold after completion. Published generating capacity is 1,400 MW. This is the original investment-decision estimate, not a newly calculated 2026 budget. Sofia offshore wind farm: 1400 MW generating project rating. Operator-reported electric generating capacity; not annual energy production
RWE[3] June 11, 2026 confirms installation of all 100 × 14 MW turbines, final turbine installation June 10. Construction/commissioning continues; the announcement does not prove full commercial operation.
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
元のタイトル: Sofia offshore wind farm — under construction / commissioning
RWEの2021年第1四半期報告は、Sofiaの想定プロジェクト投資額を約30億ポンドと公表しています。これには完成後に売却される系統接続が含まれます。公表された発電容量は1,400 MWです。これは当初の投資判断時の見積りであり、2026年向けに再計算された予算ではありません。[3][4]
RWEの2021年第1四半期報告は、Sofiaの想定プロジェクト投資額を約30億ポンドと公表しています。これには完成後に売却される系統接続が含まれます。公表された発電容量は1,400 MWです。これは当初の投資判断時の見積りであり、2026年向けに再計算された予算ではありません。Sofia洋上風力発電所:発電プロジェクトの定格は1400 MWです。事業者が報告した発電設備容量であり、年間発電量ではありません[3]
RWEは2026年6月11日、14 MWタービン100基(100 × 14 MW)すべての設置を確認しました。最後のタービンは6月10日に設置されました。建設/試運転は継続中で、この発表は完全な商業運転を裏付けるものではありません。[4]
掲載対象は、物理的な建設、試運転、または2025~2026年の開業が確認でき、プロジェクト固有の費用と電気出力が公表されているものに限ります。費用は公表された範囲と通貨を使用し、基準推計や通貨換算は行いません。MWは出力容量であり、年間発電量ではありません。年間発電量の見込みが示されている場合は予測値です。地図上の点は報告された発電所・プロジェクトの所在地であり、おおよその位置の場合があります。該当するインベントリ表示や除外された拡張提案は加算できる容量ではありません。
Sofiaアレイでの着実な進捗。設置済みタービンは80基を超えました(2026年5月)。公式プロジェクトギャラリーの写真。日付は事業者のギャラリー表記です。クレジット: RWE / Sofia Offshore Wind Farm;この画像の撮影者は不明。情報源とギャラリー;元メディア。
最後のタービンタワーが積み込まれ、洋上へ向かう準備が整いました(2026年6月)。公式プロジェクトギャラリーの写真。日付は事業者のギャラリー表記です。クレジット: RWE / Sofia Offshore Wind Farm;この画像の撮影者は不明。情報源とギャラリー;元メディア。