Pattern’s July 8, 2026 release identifies an $11 billion SunZia energy investment. This cost covers the combined wind-and-transmission project, not just a wind phase. Wind generating capacity is 3,650 MW; the separate 3,000 MW transmission rating is not additional generation. The June 18, 2026 operator announcement confirms full operation. One collection pin represents the complete project; the North/South inventory records are supporting views.
Published project-specific cost for SunZia Wind and Transmission: USD 1.1e+10. Basis: Combined wind-and-transmission capital investment; includes associated HVDC infrastructure.
Published electric generating project rating for SunZia Wind and Transmission: 3650 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Project page identifies 3,650 MW wind generation separately from transmission.
Pattern Energy announced on June 18, 2026 that SunZia Wind and its associated transmission system are fully operational. The operator reports approximately 3,650 MW for the combined wind project, spanning north/south facilities; do not assign the full-project figure to each phase or count the transmission line as generation. The operator announced the overall project fully operational June 18, 2026.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
編集@ThePinGang による
編集@ThePinGang による
変更前
変更前
Pattern Energy announced on June 18, 2026 that SunZia Wind and its associated transmission system are fully operational. The operator reports approximately 3,650 MW for the combined wind project, spanning north/south facilities; do not assign the full-project figure to each phase or count the transmission line as generation.
EIA August 2026 generator inventory, plant ID 66923: SunZia Wind South, Lincoln County, NM. Included 1 new/recent generating units with a summed nameplate rating of 2561.2 MW.
EIA reports operation at month/year precision. The date is the last day of the earliest reported operation month/year, an estimated display boundary, not an exact opening day. Different units may have later dates. Future dates are operator-reported plans, not guarantees.
Coordinates are the EIA-reported plant point, not a verified entrance. New units at existing plants are included; the total excludes older units and battery/pumped storage. Capacity is a power rating, not annual energy output. Status was reported in August and may have changed since.
GEM August 2026 snapshot: under construction. 2561.2 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Wind.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
Additional source view; compare phase coverage and rating conventions before combining figures.
編集@ThePinGang による
変更前
Pattern Energy announced on June 18, 2026 that SunZia Wind and its associated transmission system are fully operational. The operator reports approximately 3,650 MW for the combined wind project, spanning north/south facilities; do not assign the full-project figure to each phase or count the transmission line as generation.
EIA August 2026 generator inventory, plant ID 66923: SunZia Wind South, Lincoln County, NM. Included 1 new/recent generating units with a summed nameplate rating of 2561.2 MW.
EIA reports operation at month/year precision. The date is the last day of the earliest reported operation month/year, an estimated display boundary, not an exact opening day. Different units may have later dates. Future dates are operator-reported plans, not guarantees.
Coordinates are the EIA-reported plant point, not a verified entrance. New units at existing plants are included; the total excludes older units and battery/pumped storage. Capacity is a power rating, not annual energy output. Status was reported in August and may have changed since.
GEM August 2026 snapshot: under construction. 2561.2 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Wind.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
読者の写真で、出典付きのピンのメディアとは別に表示されます。
最初の項目は常にピンの出典です。全体の確度は、各資料が上記の開始・終了時刻をどれだけ強く裏付けているかの加重平均です。最新の資料より180日古くなるごとに、重みは半分になります。
文書で確認された物理的なマイルストーン、または日付付きの進捗・報告の目安。期間末の日付は報告された月・四半期のみを表し、正確な稼働日を作り出すものではない。情報源の推定値はそのように表示され、確定した将来の開業日としては扱わない。
Published project-specific cost for SunZia Wind and Transmission: USD 1.1e+10. Basis: Combined wind-and-transmission capital investment; includes associated HVDC infrastructure.[1]
Published electric generating project rating for SunZia Wind and Transmission: 3650 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Project page identifies 3,650 MW wind generation separately from transmission.[1]
Pattern Energy[2][3] announced on June 18, 2026 that SunZia Wind and its associated transmission system are fully operational. The operator reports approximately 3,650 MW for the combined wind project, spanning north/south facilities; do not assign the full-project figure to each phase or count the transmission line as generation. The operator announced the overall project fully operational June 18, 2026.
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
元のタイトル: SunZia Wind and Transmission — operational
Patternの2026年7月8日付リリースは、SunZiaへの110億ドルのエネルギー投資を明らかにしている。この費用は風力発電のみの段階ではなく、風力と送電を合わせたプロジェクト全体を対象とする。風力発電容量は3,650 MWで、別枠の送電容量3,000 MWは追加の発電能力ではない。2026年6月18日の事業者発表で全面稼働が確認された。1つのコレクションピンがプロジェクト全体を表し、北側・南側の設備記録は補足的な表示である。[2][3][4]
SunZia Wind and Transmissionの公表されたプロジェクト固有費用:USD 1.1e+10。根拠:風力と送電を合わせた資本投資で、関連するHVDCインフラを含む。[2]
SunZia Wind and Transmissionの公表された発電プロジェクト定格:3650 MW。根拠:事業者が報告した発電容量であり、年間発電量ではない。プロジェクトのページでは、3,650 MWの風力発電が送電とは別に示されている。[3]
Pattern Energyは2026年6月18日、SunZia Windと関連する送電システムが全面稼働したと発表した。事業者は、北側・南側の施設にまたがる風力プロジェクト全体で約3,650 MWと報告している。プロジェクト全体の数値を各段階に当てはめたり、送電線を発電として数えたりしてはならない。事業者は2026年6月18日に、プロジェクト全体が全面稼働したと発表した。[4]
掲載対象は、物理的な建設、試運転、または2025~2026年の開業が確認でき、プロジェクト固有の費用と電気出力が公表されているものに限ります。費用は公表された範囲と通貨を使用し、基準推計や通貨換算は行いません。MWは出力容量であり、年間発電量ではありません。年間発電量の見込みが示されている場合は予測値です。地図上の点は報告された発電所・プロジェクトの所在地であり、おおよその位置の場合があります。該当するインベントリ表示や除外された拡張提案は加算できる容量ではありません。
事業者の2026年7月のプロジェクト発表に掲載されたSunZiaの風力タービン。撮影日は別途公表されていない。クレジット:Pattern Energy、撮影者は不明。出典とギャラリー;オリジナルメディア。