BrightNight publishes no schedule; the 1 February 2029 operating date comes from EIA-860M (plant 68366, generator AGAT) as listed by Cleanview[3], and an earlier tracker listing said December 2027, so the date is only an estimate.BrightNight is proposing the Agate Storage Project, a 150 MW / 600 MWh lithium-ion battery (about 170 MW in the county SEPA filing) next to Puget Sound Energy's Foss Corner Substation near Poulsbo, Washington; no cost or schedule is published and Kitsap County's battery moratorium runs to 7 December 2026.