Energy: battery storage · 확인일 2026-10-30
확인된 단계만 강조합니다. 수치와 날짜는 계획과 입증된 상태를 구분합니다.
205 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"Hazleton","summerNetMW":205.0”
2028-06-30; requested date only, not an achieved opening.
“"projectNumber":"J3780","queueDate":"2024-04-18T04:00:00+00:00","inService":"2028-06-30T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":""”
Battery Storage; Hazleton.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J3780","queueDate":"2024-04-18T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J3780","queueDate":"2024-04-18T04:00:00+00:00","inService":"2028-06-30T04:00:00+00:00"”
이 핀은 뉴스를 계속 추적합니다. 현재까지 알려진 내용을 보여주며, 무엇이 바뀌었고 그 계기가 무엇인지 여기에 표시합니다.
수정됨@ThePinGang님이
Alliant Energy / Interstate Power and Light development of the Hazleton Clean Energy Storage Center in Buchanan County, Iowa. TheJ3780 is a 205 MW / 820 MWh battery facility connects to the 345 kV Hazleton substation hub, providing essential grid flexibility, wind generation firming, and local transmission support across northeastern Iowa.battery storage interconnection request in Buchanan, IA. The grid operator lists its queue status as Active. The requested in-service date is 2028-06-30; this is a planning date.
Alliant Energy / Interstate Power and Light advanced engineering reviews for the Hazleton Clean Energy Storage Center. Features 205 MW / 820 MWh of grid-scale battery storage capacity in Buchanan County, Iowa. RepresentsJ3780 is a 205 MW battery storage interconnection request in Buchanan, IA. The grid operator lists its queue status as Active. The requested in-service date is 2028-06-30; this is a 220 million USD private clean energy infrastructure investment in eastern Iowa. Connects to the 345 kV Hazleton substation hub within the MISO transmission footprint. Enhances grid flexibility, firms regional wind generation, and reinforces transmission reliability. Timeline: planned project targeting commercial operation in June 2028 (estimated) under MISO interconnection queue and state regulatory schedules.planning date. The point of interconnection is Hazleton. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
수정됨@ThePinGang님이
… firms regional wind generation, and reinforces transmission reliability. Timeline: planned project targeting commercial operation in June 2028 (estimated) under MISO interconnection queue and state regulatory schedules.
수정됨@ThePinGang님이
독자들의 사진으로, 출처가 있는 핀의 미디어와 별도로 표시됩니다. 먹거나 본 것을 평가하고, 레스토랑 핀에서는 사진에 바로 요리를 태그해 보세요.
첫 번째 항목은 항상 핀의 출처입니다. 전체 신뢰도는 각 자료가 위의 시작·종료 시각을 얼마나 확실히 뒷받침하는지에 대한 가중 평균이며, 자료는 최신 자료보다 180일 오래될 때마다 가중치가 절반이 됩니다.
빠지거나 잘못된 점이 있나요? 이 핀을 뒷받침하는 링크, 다른 시작일이나 종료일과 그 이유, 빠지거나 잘못된 사실을 자신의 말로 알려주세요. AI가 이 핀의 출처와 대조하고 더 나은 자료를 찾아, 뒷받침하는 페이지를 추가합니다. 핀 자체의 출처가 여전히 가장 중요하게 반영됩니다. AI는 이미지도 확인합니다. 다른 것을 보여주거나 제대로 보여주지 못하는 이미지는 뒤로 옮기거나 교체합니다.
원본 제목: Hazleton: 205 MW Battery Interconnection Request J3780
Power storage205 MW · J3780: 205 MW requested battery storage. Queue status: Active. Requested date: 2028-06-30. Not current measured generation; No annual energy or battery MWh inferred. · source