Energy: photovoltaic generation · 확인일 2026-10-30
확인된 단계만 강조합니다. 수치와 날짜는 계획과 입증된 상태를 구분합니다.
150 MW photovoltaic generation request; preliminary interconnection scope, not measured output.
“"poiName":"Fayetteville Bee Hollow Road 138 kV Substation","summerNetMW":150.0”
2025-06-30; requested date only, not an achieved opening.
“"projectNumber":"J1311","queueDate":"2019-04-29T04:00:00+00:00","inService":"2026-06-30T04:00:00+00:00"”
Done; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Done","sisPhase1":"","postGIAStatus":"Not Started"”
Solar; Fayetteville Bee Hollow Road 138 kV Substation.
“"fuelType":"Solar","facilityType":"Photovoltaic"”
Interconnection request received
“"projectNumber":"J1311","queueDate":"2019-04-29T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J1311","queueDate":"2019-04-29T04:00:00+00:00","inService":"2026-06-30T04:00:00+00:00"”
이 핀은 뉴스를 계속 추적합니다. 현재까지 알려진 내용을 보여주며, 무엇이 바뀌었고 그 계기가 무엇인지 여기에 표시합니다.
수정됨@ThePinGang님이
MISO regional transmission interconnection development of the Bee Hollow Clean Solar CenterJ1311 is a 150 MW photovoltaic generation interconnection request in St. Clair County, Illinois. Providing 150 MWac of renewable power, the utility-scale solar project feeds into Ameren Illinois transmission lines to power metro-east Illinois communities with clean, locally generated electricity.IL. The grid operator lists its queue status as Done. The requested in-service date is 2025-06-30; this is a planning date.
Invenergy progressed development filings for the Bee Hollow Clean Solar CenterJ1311 is a 150 MW photovoltaic generation interconnection request in St. Clair County, Illinois. Generates 150 MWac of clean photovoltaic power across the metro-east St. Louis region. Represents an estimated 170 million USD renewable infrastructure investment. Connects to Ameren Illinois transmission lines along the State Route 15 corridor. Supplies emissions-free electricity under long-term power purchase agreements. Timeline: planned project targeting commercial operation IL. The grid operator lists its queue status as Done. The requested in-service date is 2025-06-30; this is a planning date. The point of interconnection is Fayetteville Bee Hollow Road 138 kV Substation. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in November 2026 (estimated) under MISO interconnection queue and state regulatory schedules.the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
수정됨@ThePinGang님이
… Supplies emissions-free electricity under long-term power purchase agreements. Timeline: planned project targeting commercial operation in November 2026 (estimated) under MISO interconnection queue and state regulatory schedules.
독자들의 사진으로, 출처가 있는 핀의 미디어와 별도로 표시됩니다. 먹거나 본 것을 평가하고, 레스토랑 핀에서는 사진에 바로 요리를 태그해 보세요.
첫 번째 항목은 항상 핀의 출처입니다. 전체 신뢰도는 각 자료가 위의 시작·종료 시각을 얼마나 확실히 뒷받침하는지에 대한 가중 평균이며, 자료는 최신 자료보다 180일 오래될 때마다 가중치가 절반이 됩니다.
빠지거나 잘못된 점이 있나요? 이 핀을 뒷받침하는 링크, 다른 시작일이나 종료일과 그 이유, 빠지거나 잘못된 사실을 자신의 말로 알려주세요. AI가 이 핀의 출처와 대조하고 더 나은 자료를 찾아, 뒷받침하는 페이지를 추가합니다. 핀 자체의 출처가 여전히 가장 중요하게 반영됩니다. AI는 이미지도 확인합니다. 다른 것을 보여주거나 제대로 보여주지 못하는 이미지는 뒤로 옮기거나 교체합니다.
원본 제목: Bee Hollow: 150 MW Solar Interconnection Request J1311
Power generation150 MW · J1311: 150 MW requested photovoltaic generation. Queue status: Done. Requested date: 2025-06-30. Not current measured generation; No annual energy or battery MWh inferred. · source