첫 번째 항목은 항상 핀의 출처입니다. 전체 신뢰도는 각 자료가 위의 시작·종료 시각을 얼마나 확실히 뒷받침하는지에 대한 가중 평균이며, 자료는 최신 자료보다 180일 오래될 때마다 가중치가 절반이 됩니다.
시작은 Epoch[3][6]의 관찰된 개간(2025-09-27)입니다. 종료는 Epoch의 예상 전체 작업 시간(2028-12-31)으로, 개발자 날짜가 아닌 추정치입니다. 핀의 기존 시작일(2028-12-28)은 착공 날짜가 아닌 예상 날짜입니다.
Cited in the project timeline.[1]
Construction research 2026-10-24: Epoch’s[1][6] 2026-03-23 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Steel framing and roofing is underway for Building 1.” Dated observation 2026-03-23; future trajectory rows and modeled costs are distinguished from this physical milestone.
Photo caption and image of Burlington construction May 4, 2026[1]
| 2026-01-04 | 건물 기초 공사의 작은 부분이 시작되고 토지 정리가 대부분 완료된 것으로 보입니다. |
|---|
| 2026-03-23 | 1호관의 철골 및 지붕 공사가 진행 중입니다. |
|---|
| 2028-12-31 | 모든 건물이 완공되어 현장이 완전히 운영되고 있습니다. 우리의 추론은 지금까지의 사례가 토지 개간에서 1GW에 도달하는 데 평균 2~2.5년이 걸린다는 것입니다. 이는 대략 2028-01-01을 의미합니다. 그러나 디 |
|---|
날짜순으로 표시된 Epoch AI 위성 이미지 메모입니다. · 출처
548,950 sq ft, single story, four data halls
“will comprise a single-story 548,950 square foot (51,000 sqm) data center with four data halls.”
1.2 GW planned
“build and operate the previously announced 1.2 GW Stargate data center in Milam County, Texas.”
15 October (2026) / Q4 2028
“All buildings finished, site is fully operational.”
Building 1 steel and roofing; no building confirmed operational
“Steel framing and roofing is underway for Building 1.”
Land clearing begins (Epoch satellite observation)
“Land clearing begins for the site”
Building foundation construction begins
“Small sections of building foundation construction begins, and land clearing appears to be mostly finished”
SB Energy to build and operate the 1.2 GW site; OpenAI and SoftBank invest $1B in SB Energy
“SB Energy will provide the project's powered infrastructure, while SoftBank and OpenAI invest $1 billion in the company to support its growth”
Steel framing and roofing underway for Building 1
“Steel framing and roofing is underway for Building 1.”
TDLR filing for Freebird Phase 1: 548,950 sq ft, four data halls, about $470 million
“The filing discloses the estimated cost of the project at $470 million, with a project completion date of 15 October.”
Phase 1 completion date in TDLR filing (no confirmation of completion published)
“with a project completion date of 15 October.”
Full site fully operational (Epoch projection)
“All buildings finished, site is fully operational.”
빠지거나 잘못된 점이 있나요? 이 핀을 뒷받침하는 링크, 다른 시작일이나 종료일과 그 이유, 빠지거나 잘못된 사실을 자신의 말로 알려주세요. AI가 이 핀의 출처와 대조하고 더 나은 자료를 찾아, 뒷받침하는 페이지를 추가합니다. 핀 자체의 출처가 여전히 가장 중요하게 반영됩니다. AI는 이미지도 확인합니다. 다른 것을 보여주거나 제대로 보여주지 못하는 이미지는 뒤로 옮기거나 교체합니다.
원본 제목: OpenAI Stargate Milam AI Data Center Buildout
텍사스주 벌링턴 근처에 있는 OpenAI의 Stargate Milam 캠퍼스는 SoftBank의 SB Energy가 구축하고 운영할 예정인 1.2GW 규모의 데이터 센터입니다. 위성 이미지는 2026년 3월까지 1번 건물의 강철 프레임과 지붕을 보여주며, 1단계에 대한 주정부 서류에는 548,950평방피트와 약 4억 7천만 달러가 기재되어 있습니다. Epoch AI는 2028년 말까지 완전한 가동을 계획하고 있습니다. 아직 가동이 확인된 건물은 없습니다.
Epoch의 2026-03-23 관찰 문서에는 이 명명된 빌드아웃에 대한 물리적 건설/설치가 남아 있습니다. 진행 중(In Progress)은 이전 운영 건물이나 미래 용량을 완료하지 않습니다. 전력 및 가속기 수는 운영자 인증 등급이 아닌 Epoch 추정치로 유지됩니다. 모델링된 2025달러 자본 비용에는 컴퓨팅 하드웨어가 포함되며 소스 기반 건설 예산이 아닙니다.