Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 출처
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 출처
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 출처
| Date | Observed status |
|---|---|
| 2024-05-31 | Land clearing begins for northern two buildings (Building 1-2) |
| 2025-06-28 | Building 1 looks close to finishing construction, with chillers in place. OpenAI [stated](https://openai.com/index/five-new-stargate-sites/) that "Oracle began delivering the first NVIDIA GB200 racks |
| 2025-09-26 | Building 1 is fully operational around this date. The first phase was "live" on September 30 according a Crusoe [announcement](https://www.crusoe.ai/resources/newsroom/crusoe-announces-flagship-abilen |
| 2025-12-24 | Building 2 is fully operational. This exact date corresponds to the expected completion date of "Four (4) data hall spaces and an administrative office build-out" according to a [TDLR filing](https:// |
| 2026-01-15 | The 1 GW substation looks close to completion. Building 3 appears to have all power and cooling equipment installed, but there are still signs of construction work. This seems on track for operation i |
| 2026-03-24 | Building 3 and 4 look complete, but are not fully operational. Not as many cars are parked next to it as Building 1-2 which suggests they may still be ramping up. Building 4 was due by now according t |
| 2026-05-23 | Buildings 3 and 4 are estimated to be operational. On April 22nd, Oracle [posted](https://x.com/i/status/2047012589302153558) that "In Abilene, 200MW is already operational". This suggests that there |
| 2026-07-28 | Buildings 5-8 are structurally complete and roofed but not yet confirmed operational (fit-out ongoing). The substation looks complete. |
| 2026-09-10 | Buildings 5-6 are operational. On Oracle's Q1 FY27 earnings call (September 10, 2026), Clay Magouyrk said "6 of the 8 campus buildings, representing 618 megawatts and 75% of total capacity have now be |
| 2026-11-01 | Buildings 7-8 are estimated to be operational. On March 24, Building 8 roughly looked like where Building 3 was in September. Building 3 is estimated to be operational in April, 7 months later. This n |
Epoch AI satellite-imagery notes, in date order. · 출처
건설 중
Data center · 확인일 2026-10-31
확인된 단계만 강조합니다. 수치와 날짜는 계획과 입증된 상태를 구분합니다.
$15 billion
“announced the second phase of a $15 billion joint venture to fund the campus.”
About 4 million sq ft, eight buildings
“bringing the campus to eight buildings, about 4 million square feet and 1.2 gigawatts”
875 acres
“sits Stargate — an 875-acre AI data center campus”
618 MW delivered of 824 MW IT projected (Epoch); campus 1.2 GW grid-level design
“said six of the eight buildings, representing 618 megawatts and 75 percent of the campus, had been delivered”
Six of eight buildings delivered; Buildings 7-8 fit-out
“Buildings 5-6 are operational.”
Land clearing begins for Buildings 1-2 (Epoch satellite observation)
“Land clearing begins for northern two buildings (Building 1-2)”
City council approves 85%, 10-year tax abatements
“The Abilene City Council approved 85 percent, 10-year property tax abatements for the site in February 2025”
Second phase of six more buildings announced (eight total, 1.2 GW)
We got taken, we got robbed,
So were there things we could have done different? Of course there were,
Who exactly is paying for all of this?
come to Abilene every day to build the future of AI infrastructure
독자들의 사진으로, 출처가 있는 핀의 미디어와 별도로 표시됩니다. 먹거나 본 것을 평가하고, 레스토랑 핀에서는 사진에 바로 요리를 태그해 보세요.
첫 번째 항목은 항상 핀의 출처입니다. 전체 신뢰도는 각 자료가 위의 시작·종료 시각을 얼마나 확실히 뒷받침하는지에 대한 가중 평균이며, 자료는 최신 자료보다 180일 오래될 때마다 가중치가 절반이 됩니다.
시작은 Epoch[3][7]의 위성 관측 토지 개간입니다. Crusoe는 건설이 2024년 6월에 시작되었다고 밝혔습니다. 건물 7-8의 운영은 Epoch의 추정에 따르면 2026년 11월에 종료됩니다. 개발자 날짜는 게시되지 않습니다.
Cited in the project timeline.[1]
Construction research 2026-10-24: Epoch’s[1][7] 2026-07-28 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “not yet confirmed operational” Dated observation 2026-07-28; future trajectory rows and modeled costs are distinguished from this physical milestone.
Cited in the project timeline.[1]
빠지거나 잘못된 점이 있나요? 이 핀을 뒷받침하는 링크, 다른 시작일이나 종료일과 그 이유, 빠지거나 잘못된 사실을 자신의 말로 알려주세요. AI가 이 핀의 출처와 대조하고 더 나은 자료를 찾아, 뒷받침하는 페이지를 추가합니다. 핀 자체의 출처가 여전히 가장 중요하게 반영됩니다. AI는 이미지도 확인합니다. 다른 것을 보여주거나 제대로 보여주지 못하는 이미지는 뒤로 옮기거나 교체합니다.
원본 제목: OpenAI Stargate Abilene AI Data Center Buildout
텍사스주 애빌린에 있는 OpenAI의 Stargate 캠퍼스는 Crusoe의 8개 건물로, 약 400만 평방피트, 1.2GW 규모로 Oracle에 임대되었습니다. 2024년에 공사가 시작되었습니다. 오라클은 8개의 건물 중 6개가 2026년 9월 10일에 인도되었으며, 마지막 2개는 아직 장착 중이라고 보고했습니다. 150억 달러 규모의 합작 투자로 캠퍼스 자금을 조달합니다. Epoch AI는 현재 IT 전력이 618MW, 완료되면 824MW로 추정합니다.
Epoch의 2026-07-28 관찰 문서에는 이 명명된 빌드아웃에 대한 물리적 건설/설치가 남아 있습니다. 진행 중(In Progress)은 이전 운영 건물이나 미래 용량을 완료하지 않습니다. 전력 및 가속기 수는 운영자 인증 등급이 아닌 Epoch 추정치로 유지됩니다. 모델링된 2025달러 자본 비용에는 컴퓨팅 하드웨어가 포함되며 소스 기반 건설 예산이 아닙니다.
주석이 달린 위성 발자국(물리적 부품 70개)을 사용하여 Epoch AI가 추적하는 대규모 개척지 AI 교육 및 추론 캠퍼스입니다.
“announced a second phase of six more buildings, bringing the campus to eight buildings, about 4 million square feet and 1.2 gigawatts”
$15 billion Crusoe/Blue Owl/Primary Digital joint venture announced for the campus
“On May 21, 2025, Crusoe, Blue Owl Capital and Primary Digital Infrastructure announced the second phase of a $15 billion joint venture to fund the campus.”
Buildings 1-2 live on Oracle Cloud Infrastructure
“Crusoe said on Sept. 30, 2025, that the first phase was running on Oracle Cloud Infrastructure”
Crusoe tops out the eighth and final building
“Crusoe has marked a major milestone in its AI infrastructure expansion by topping out the eighth and final building”
Building 2 fully operational (Epoch estimate; matches TDLR completion date)
“Building 2 is fully operational.”
OpenAI and Oracle drop plan to expand Abilene beyond about 1.2 GW
“OpenAI had planned to expand this site to 2.1 GW, but recently reversed course”
Buildings 5-8 structurally complete and roofed; fit-out ongoing
“Buildings 5-8 are structurally complete and roofed but not yet confirmed operational (fit-out ongoing).”
Oracle: six of eight buildings, 618 MW, delivered
“said six of the eight buildings, representing 618 megawatts and 75 percent of the campus, had been delivered”
Buildings 7-8 estimated operational (full campus; Oracle gave no date)
“Buildings 7-8 are estimated to be operational.”