Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 출처
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 출처
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 출처
| Date | Observed status |
|---|---|
| 2023-10-31 | Start of construction for the first building, according to [Applied Digital](https://ir.applieddigital.com/news-events/press-releases/detail/75/applied-digital-announces-groundbreaking-of). CoreWeave |
| 2025-05-28 | CoreWeave signed the first lease package for 250 MW. No buildings online yet. This is according to an [SEC 8-k filing](https://www.sec.gov/Archives/edgar/data/1144879/000164117225013199/form8-k.htm) f |
| 2025-08-29 | [A new 150 MW lease](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with) brings CoreWeave to 400 MW total contracted. The project |
| 2025-10-27 | The first 50 MW slice of Building 1 has reached Ready for Service status according to [this report](https://ir.applieddigital.com/news-events/press-releases/detail/133/applied-digital-achieves-ready-f |
| 2025-11-24 | [This Applied Digital report](https://ir.applieddigital.com/news-events/press-releases/detail/137/applied-digital-completes-phase-ii-ready-for-service-at) says the rest of Building 1 has reached Ready |
| 2026-03-27 | According to satellite imagery, Building 1 looks complete and in service, with the surrounding power/cooling equipment also operational. (Note: this image doesn't provide a view of buildings 2 or 3, t |
| 2026-06-30 | According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and |
| 2026-12-31 | According to the [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 2 should be online sometime in the seco |
| 2027-06-01 | According to [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 3 should come online in the first half of 2 |
Epoch AI satellite-imagery notes, in date order. · 출처
건설 중
Digital infrastructure: AI data-center campus buildout · 확인일 2026-10-30
확인된 단계만 강조합니다. 수치와 날짜는 계획과 입증된 상태를 구분합니다.
Epoch’s current campus estimate: 68 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 68 MW”
Physical-stage observation dated 2026-06-30. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Building 3 construction is well underway”
Epoch’s dated 2026-06-30 assessment: Building 3 construction is well underway Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Building 3 construction is well underway”
Epoch estimates AI hardware: Nvidia B200 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Nvidia B200 chips.”
Epoch dated observation: CoreWeave was not leased yet at this site, but this is the…
“CoreWeave was not leased yet at this site, but this is the construction start date we're using for relevance.”
Epoch dated observation: According to satellite imagery, Building 2 is fully roofed and shell…
“According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed.”
독자들의 사진으로, 출처가 있는 핀의 미디어와 별도로 표시됩니다. 먹거나 본 것을 평가하고, 레스토랑 핀에서는 사진에 바로 요리를 태그해 보세요.
첫 번째 항목은 항상 핀의 출처입니다. 전체 신뢰도는 각 자료가 위의 시작·종료 시각을 얼마나 확실히 뒷받침하는지에 대한 가중 평균이며, 자료는 최신 자료보다 180일 오래될 때마다 가중치가 절반이 됩니다.
저장된 날짜는 확인된 정확한 개장일이 아닌 예상 추적 또는 용량 궤적 표시입니다. 건설 상태는 인용된 날짜의 물리적 범위를 따릅니다. 경과된 목표에서는 완료가 추론되지 않습니다.
Construction research 2026-10-24: Epoch’s[1] 2026-06-30 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Building 3 construction is well underway” Dated observation 2026-06-30; future trajectory rows and modeled costs are distinguished from this physical milestone.
빠지거나 잘못된 점이 있나요? 이 핀을 뒷받침하는 링크, 다른 시작일이나 종료일과 그 이유, 빠지거나 잘못된 사실을 자신의 말로 알려주세요. AI가 이 핀의 출처와 대조하고 더 나은 자료를 찾아, 뒷받침하는 페이지를 추가합니다. 핀 자체의 출처가 여전히 가장 중요하게 반영됩니다. AI는 이미지도 확인합니다. 다른 것을 보여주거나 제대로 보여주지 못하는 이미지는 뒤로 옮기거나 교체합니다.
원본 제목: CoreWeave Ellendale ND AI Data Center Buildout
Epoch의 2026-06-30 관찰 문서에는 이 명명된 빌드아웃에 대한 물리적 구성/설치가 남아 있습니다. 진행 중(In Progress)은 이전 운영 건물이나 미래 용량을 완료하지 않습니다. 전력 및 가속기 수는 운영자 인증 등급이 아닌 Epoch 추정치로 유지됩니다. 모델링된 2025달러 자본 비용에는 컴퓨팅 하드웨어가 포함되며 소스 기반 건설 예산이 아닙니다.
주석이 달린 위성 풋프린트(8개의 물리적 부품)를 사용하여 Epoch AI가 추적하는 하이퍼스케일 프론티어 AI 교육 및 추론 캠퍼스.