2028. Entergy’s April 2026 groundbreaking release identifies Legend and Lone Star as physically progressing projects expected to begin serving customers in 2028.
Construction is verified; the completion date remains an estimate. The timeline marker represents the published target year/month, not a confirmed opening day.
Entergy’s September 11, 2025 approval release gives a $1.6 billion investment for Legend, updating the earlier $1.46 billion proposal. The operator’s design rating is 754 MW and physical groundbreaking occurred April 9, 2026. Economic-impact and customer-benefit figures are not the construction budget.
Published project-specific cost for Legend Power Station: USD 1.6e+09. Basis: Published project-specific capital/construction estimate.
Published electric generating project rating for Legend Power Station: 754 MW. Basis: Operator-reported electric generating capacity; not annual energy production. The operator identifies Legend as a 754 MW combined-cycle plant.
Entergy’s April 9, 2026 announcement confirms groundbreaking on Legend in Port Arthur and Lone Star near Cleveland. Both were approved by the PUCT in 2025 and are expected to serve customers in 2028. The combined projects exceed 1,200 MW; that combined figure is not the capacity of either plant alone. April 9, 2026 groundbreaking verifies physical construction; target service is 2028.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Joint groundbreaking ceremony for Legend and Lone Star power stations in Port Arthur, Texas, April 9, 2026. This is the shared project ceremony, not a photograph of a completed Lone Star plant or its Cleveland-area construction site. Credit: Office of the Texas Governor, via Entergy Texas. Source and gallery; original media.
수정됨@ThePinGang님이
변경 전
2028. Entergy’s April 2026 groundbreaking release identifies Legend and Lone Star as physically progressing projects expected to begin serving customers in 2028.
Construction is verified; the completion date remains an estimate. The timeline marker represents the published target year/month, not a confirmed opening day.
Entergy’s September 11, 2025 approval release gives a $1.6 billion investment for Legend, updating the earlier $1.46 billion proposal. The operator’s design rating is 754 MW and physical groundbreaking occurred April 9, 2026. Economic-impact and customer-benefit figures are not the construction budget.
Published project-specific cost for Legend Power Station: USD 1.6e+09. Basis: Published project-specific capital/construction estimate.
Published electric generating project rating for Legend Power Station: 754 MW. Basis: Operator-reported electric generating capacity; not annual energy production. The operator identifies Legend as a 754 MW combined-cycle plant.
Entergy’s April 9, 2026 announcement confirms groundbreaking on Legend in Port Arthur and Lone Star near Cleveland. Both were approved by the PUCT in 2025 and are expected to serve customers in 2028. The combined projects exceed 1,200 MW; that combined figure is not the capacity of either plant alone. April 9, 2026 groundbreaking verifies physical construction; target service is 2028.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
수정됨@ThePinGang님이
수정됨@ThePinGang님이
변경 전
변경 전
Entergy’s September 11, 2025 approval release gives a $1.6 billion investment for Legend, updating the earlier $1.46 billion proposal. The operator’s design rating is 754 MW and physical groundbreaking occurred April 9, 2026. Economic-impact and customer-benefit figures are not the construction budget.
Published project-specific cost for Legend Power Station: USD 1.6e+09. Basis: Published project-specific capital/construction estimate.
Published electric generating project rating for Legend Power Station: 754 MW. Basis: Operator-reported electric generating capacity; not annual energy production. The operator identifies Legend as a 754 MW combined-cycle plant.
Entergy’s April 9, 2026 announcement confirms groundbreaking on Legend in Port Arthur and Lone Star near Cleveland. Both were approved by the PUCT in 2025 and are expected to serve customers in 2028. The combined projects exceed 1,200 MW; that combined figure is not the capacity of either plant alone. April 9, 2026 groundbreaking verifies physical construction; target service is 2028.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
수정됨@ThePinGang님이
변경 전
변경 전
Entergy’s April 9, 2026 announcement confirms groundbreaking on Legend in Port Arthur and Lone Star near Cleveland. Both were approved by the PUCT in 2025 and are expected to serve customers in 2028. The combined projects exceed 1,200 MW; that combined figure is not the capacity of either plant alone.
EIA August 2026 generator inventory, plant ID 68053: Legend Power Station, Jefferson County, TX. Included 1 new/recent generating units with a summed nameplate rating of 754 MW.
EIA reports operation at month/year precision. The date is the last day of the earliest reported operation month/year, an estimated display boundary, not an exact opening day. Different units may have later dates. Future dates are operator-reported plans, not guarantees.
Coordinates are the EIA-reported plant point, not a verified entrance. New units at existing plants are included; the total excludes older units and battery/pumped storage. Capacity is a power rating, not annual energy output. Status was reported in August and may have changed since.
독자 사진으로, 출처가 있는 핀 미디어와 따로 표시됩니다.
첫 번째 항목은 항상 핀의 출처입니다. 전체 신뢰도는 각 자료가 위의 시작·종료 시각을 얼마나 확실히 뒷받침하는지에 대한 가중 평균이며, 자료는 최신 자료보다 180일 오래될 때마다 가중치가 절반이 됩니다.
공표된 목표: 2028년. 건설은 확인되지만, 이 미래의 완공/가동 시점은 추정이다. 이 날짜는 연말/월말 타임라인 표시일 뿐 확정된 정확한 개장일이 아니다. 출처: https://www.entergy[3][4][5].com/news/entergy-texas-breaks-ground-legend-and-lone-star
Legend Power Station design rendering from the upper panel of Entergy[3][4][5] Texas’s February 4, 2026 presentation, PDF page 10. This is the Legend panel, not the Lone Star design below it, and is not an as-built photograph.
Published project-specific cost for Legend Power Station: USD 1.6e+09. Basis: Published project-specific capital/construction estimate.[1]
Published electric generating project rating for Legend Power Station: 754 MW. Basis: Operator-reported electric generating capacity; not annual energy production. The operator identifies Legend as a 754 MW combined-cycle plant.[1]
Entergy’s[3][4] April 9, 2026 announcement confirms groundbreaking on Legend in Port Arthur and Lone Star near Cleveland. Both were approved by the PUCT in 2025 and are expected to serve customers in 2028. The combined projects exceed 1,200 MW; that combined figure is not the capacity of either plant alone. April 9, 2026 groundbreaking verifies physical construction; target service is 2028.
빠지거나 잘못된 점이 있나요? 이 핀을 뒷받침하는 링크, 다른 시작일이나 종료일과 그 이유, 빠지거나 잘못된 사실을 자신의 말로 알려주세요. AI가 이 핀의 출처와 대조하고 더 나은 자료를 찾아, 뒷받침하는 페이지를 추가합니다. 핀 자체의 출처가 여전히 가장 중요하게 반영됩니다. AI는 이미지도 확인합니다. 다른 것을 보여주거나 제대로 보여주지 못하는 이미지는 뒤로 옮기거나 교체합니다.
원본 제목: Legend Power Station — estimated target 2028
2028년. Entergy의 2026년 4월 착공 발표문은 Legend와 Lone Star를 실제로 공사가 진행 중인 프로젝트로 규정하며 2028년에 고객 공급을 시작할 것으로 예상한다고 밝혔다.[5]
건설은 확인되었으나 완공일은 여전히 추정치입니다. 타임라인 표시는 공표된 목표 연도/월을 나타내며 확정된 개통일이 아닙니다.
Entergy의 2025년 9월 11일 승인 발표문은 Legend에 대한 투자액을 16억 달러로 제시해, 이전 제안액 14.6억 달러를 갱신했다. 사업자의 설계 정격은 754 MW이며 실제 착공은 2026년 4월 9일에 이뤄졌다. 경제 효과와 고객 편익 수치는 건설 예산이 아니다.[3][4][5]
Legend Power Station의 공표된 프로젝트별 비용: USD 1.6e+09. 근거: 공표된 프로젝트별 자본/건설 추정치.[3]
Legend Power Station의 공표된 발전 프로젝트 정격: 754 MW. 근거: 사업자가 보고한 발전 용량이며 연간 발전량이 아니다. 사업자는 Legend를 754 MW 복합화력 발전소로 밝히고 있다.[4]
Entergy의 2026년 4월 9일 발표는 Port Arthur의 Legend와 Cleveland 인근 Lone Star의 착공을 확인했다. 두 발전소 모두 2025년 PUCT의 승인을 받았으며 2028년에 고객 공급을 시작할 예정이다. 두 프로젝트를 합치면 1,200 MW를 넘지만, 이 합계는 어느 한 발전소만의 용량이 아니다. 2026년 4월 9일 착공은 실제 건설을 입증하며, 공급 목표 시점은 2028년이다.[5]
실제 건설, 시운전 또는 2025–2026년 개통이 확인되고 사업별 비용과 전기 출력이 공표된 사업만 포함합니다. 비용은 공표된 범위와 통화를 사용하며 기준 추정치나 환율 환산은 쓰지 않습니다. MW는 출력 용량이며 연간 전력 생산량이 아닙니다. 예상 연간 에너지가 제시된 경우 이는 예측치입니다. 지도의 점은 보고된 발전소/사업 위치이며 대략적일 수 있습니다. 일치하는 인벤토리 보기와 제외된 확장 제안은 합산할 수 있는 용량이 아닙니다.
Entergy Texas의 2026년 2월 4일자 발표 자료 상단 패널(PDF 10쪽)에서 가져온 Legend Power Station 설계 렌더링이다. 이는 Legend 패널이며 그 아래의 Lone Star 설계가 아니고, 준공 사진도 아니다. 출처: Entergy Texas, TXCPA가 게시한 Jessica Hill의 발표 자료. 출처 및 갤러리; 원본 미디어.