Amerada Storage LLC has executed a generator interconnection agreement for the 160M USD, 150.8 MW / 603 MWh utility battery storage facility in Terry County, Texas, firming South Plains renewable power on the ERCOT grid.ERCOT identifies Amerada Storage as 26INR0084, Amerada Solar LLC, 150.78 MW in Freestone County, targeting July 21, 2028. Screening is complete and full study started without an IA; this is a development request.
Amerada Storage LLC secured an executed Standard Generation Interconnection Agreement under ERCOT queue 25INR0311. Delivers 150.8 MW / 603 MWh of four-hour lithium iron phosphate energy storage to support West Texas grid reliability. Represents an estimated 160 million USD clean energy capital investment in Terry County near Brownfield. Interconnects to the local 115 kV transmission network operated by Oncor Electric Delivery. Buffers high-capacity regional wind andThe Richland–Big Brown 345 kV tap is the battery POI. Former 25INR0311 is Riverbend Storage SLF in Falls County, not Amerada. Terry County, $160M, 603 MWh and four-hour duration are unsupported. EIA plant 67649 supplies nearby Amerada solar reporting context at 31.861926, -96.11463, with 300 MW solar and a July 2029 proposal. This is not a verified battery parcel, battery rating or battery COD; solar generation while mitigating ERCOT transmission congestion. Timeline: planned project targeting commercial operation in December 2027 (estimated) under ERCOT interconnection queue and state regulatory schedules.operator Cypress Creek is not silently assigned as battery parent. Timeline: ERCOT battery projected COD; separate EIA solar schedule is not substituted.
Disuntingoleh @ThePinGang
… and solar generation while mitigating ERCOT transmission congestion. Timeline: planned project targeting commercial operation in December 2027 (estimated) under ERCOT interconnection queue and state regulatory schedules.
Foto daripada pembaca, berasingan daripada media bersumber pin. Nilaikan apa yang anda makan atau lihat, dan pada pin restoran, tag hidangan terus pada foto anda.
Entri pertama sentiasa sumber pin. Keyakinan keseluruhan ialah purata berpemberat bagi sejauh mana setiap rujukan menyokong masa mula dan tamat yang digunakan di atas; sesebuah rujukan diambil kira separuh kurang bagi setiap 180 hari lebih lama daripada yang terbaharu.
Ada yang tertinggal atau salah? Nyatakan dengan kata-kata anda sendiri: pautan yang menyokong pin ini, tarikh mula atau tamat yang berbeza beserta sebabnya, atau fakta yang tiada atau tersilap. AI menyemaknya berbanding sumber pin ini, mencari yang lebih baik, dan menambah mana-mana halaman yang menyokong anda. Sumber pin itu sendiri tetap paling diambil kira. Gambar yang menunjukkan sesuatu yang lain, atau menunjukkannya dengan buruk, turut dilihat, dan dialihkan ke bawah atau diganti.
Tajuk asal: Amerada Storage: 150.78 MW Request in Freestone County, July 2028 Target
Power storage150.8 MW · Proposed/reported scope, not measured output or evidence of operation. ERCOT identifies Amerada Storage as 26INR0084, Amerada Solar LLC, 150.78 MW in Freestone County, targeting July 21, 2028. Screening is complete and full study started wit · source