Energy: battery storage · Disemak 2026-10-30
Hanya peringkat yang dilaporkan diserlahkan. Angka dan tarikh membezakan rancangan daripada hasil dibuktikan.
400 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"PERE MARQUETTE","summerNetMW":400.0”
2030-06-30; requested date only, not an achieved opening.
“"projectNumber":"J4093","queueDate":"2025-10-06T04:00:00+00:00","inService":"2030-06-30T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":""”
Battery Storage; PERE MARQUETTE.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J4093","queueDate":"2025-10-06T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J4093","queueDate":"2025-10-06T04:00:00+00:00","inService":"2030-06-30T04:00:00+00:00"”
Pin ini mengikuti berita: ia menunjukkan apa yang diketahui sekarang, dan inilah apa yang berubah serta apa yang menyebabkannya.
Disuntingoleh @ThePinGang
Consumers Energy development of the Pere Marquette Clean Energy Storage Center in Mason County, Michigan. ProvidingJ4093 is a 400 MW / 1,600 MWh of utility-scale four-hour battery storage, the system interfaces with western Michigan transmission to balance fluctuating Lake Michigan wind generation and support grid reliability following coal plant retirements.battery storage interconnection request in Mason, MI. The grid operator lists its queue status as Active. The requested in-service date is 2030-06-30; this is a planning date.
Consumers Energy progressed state regulatory filings for the Pere Marquette Clean Energy Storage CenterJ4093 is a 400 MW battery storage interconnection request in Mason County. Supplies 400 MW / 1,600 MWh of four-hour duration battery energy storage capacity. Represents an estimated 420 million USD clean infrastructure investment in western Michigan. Interfaces with MISO high-voltage transmission lines near Lake Michigan shores. Balances regional wind generation and replaces capacity following the retirement of legacy coal facilities. Timeline: planned project targeting commercial operation in June 2030 (estimated) under MISO interconnection queue and state regulatory schedules.Mason, MI. The grid operator lists its queue status as Active. The requested in-service date is 2030-06-30; this is a planning date. The point of interconnection is PERE MARQUETTE. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
Disuntingoleh @ThePinGang
… capacity following the retirement of legacy coal facilities. Timeline: planned project targeting commercial operation in June 2030 (estimated) under MISO interconnection queue and state regulatory schedules.
Disuntingoleh @ThePinGang
Foto daripada pembaca, berasingan daripada media bersumber pin. Nilaikan apa yang anda makan atau lihat, dan pada pin restoran, tag hidangan terus pada foto anda.
Entri pertama sentiasa sumber pin. Keyakinan keseluruhan ialah purata berpemberat bagi sejauh mana setiap rujukan menyokong masa mula dan tamat yang digunakan di atas; sesebuah rujukan diambil kira separuh kurang bagi setiap 180 hari lebih lama daripada yang terbaharu.
Ada yang tertinggal atau salah? Nyatakan dengan kata-kata anda sendiri: pautan yang menyokong pin ini, tarikh mula atau tamat yang berbeza beserta sebabnya, atau fakta yang tiada atau tersilap. AI menyemaknya berbanding sumber pin ini, mencari yang lebih baik, dan menambah mana-mana halaman yang menyokong anda. Sumber pin itu sendiri tetap paling diambil kira. Gambar yang menunjukkan sesuatu yang lain, atau menunjukkannya dengan buruk, turut dilihat, dan dialihkan ke bawah atau diganti.
Tajuk asal: Pere Marquette: 400 MW Battery Interconnection Request J4093
Power storage400 MW · J4093: 400 MW requested battery storage. Queue status: Active. Requested date: 2030-06-30. Not current measured generation; No annual energy or battery MWh inferred. · source