Energy: photovoltaic generation · Disemak 2026-10-29
Hanya peringkat yang dilaporkan diserlahkan. Angka dan tarikh membezakan rancangan daripada hasil dibuktikan.
75 MW electrical generation nameplate in September 2026 preliminary planned inventory; not operating output.
“Caverns Solar Map Map FL Jackson FPL IPP Non-CHP CVSO 75 75 75 Solar Photovoltaic SUN PV”
Planned operation 2029-12; preliminary survey estimate, not a capacity commitment or achieved milestone.
“12 2029 (L) Regulatory approvals pending. Not under construction”
EIA reports (L) Regulatory approvals pending. Not under construction. A planned operation date is not evidence of commercial service.
“(L) Regulatory approvals pending. Not under construction”
Technology: Solar Photovoltaic. Plant 68331; selected generator IDs CVSO. Scope is the named solar generating component, not unrelated units at the site.
“Solar Photovoltaic”
Reported operation forecast
“12 2029 (L) Regulatory approvals pending. Not under construction”
Pin ini mengikuti berita: ia menunjukkan apa yang diketahui sekarang, dan inilah apa yang berubah serta apa yang menyebabkannya.
Disuntingoleh @ThePinGang
The Caverns Solar Project is a 75 MWac photovoltaic facility planned across rural agricultural acreage near Marianna and Florida Caverns State Park75 MW solar PV plant in Jackson County, Florida. Permitted under the Florida Department of Environmental Protection (DEP) environmental resource frameworkFlorida, listed in EIA-860M data with operator CVSO, LLC and interconnecting into the Florida Panhandle 115 kV transmission network, the single-axis tracking solar array provides clean, renewable wholesale power to rural electric cooperatives and municipal utilities.a proposed completion of December 2029. No developer announcement or site was found.
Nameplate capacity:Planned 75 MWac utility-scale single-axis trackingMW solar photovoltaic installation. Acreage: Encompasses approximately 580 acres of rural timberland and pasture north of MariannaPV plant in Jackson County. Transmission tie: Interties with the regional 115 kV bulk power transmission line in northwestCounty, Florida. Environmental conservation: Engineered with designated vegetative buffer zones to preserve local hydrology. Clean generation: Expected to generate approximately 155,000 MWh of zero-carbon power annually. Timeline: Commercial operation targeted forOperator listed as CVSO, LLC; proposed completion December 2029 following site preparation and electrical interconnection.2029.
Foto daripada pembaca, berasingan daripada media bersumber pin. Nilaikan apa yang anda makan atau lihat, dan pada pin restoran, tag hidangan terus pada foto anda.
Entri pertama sentiasa sumber pin. Keyakinan keseluruhan ialah purata berpemberat bagi sejauh mana setiap rujukan menyokong masa mula dan tamat yang digunakan di atas; sesebuah rujukan diambil kira separuh kurang bagi setiap 180 hari lebih lama daripada yang terbaharu.
Tarikh cadangan EIA-860M ditunjukkan oleh interconnection.fyi dan Cleanview[2] (Disember 2029); tiada tarikh yang pasti.
Ada yang tertinggal atau salah? Nyatakan dengan kata-kata anda sendiri: pautan yang menyokong pin ini, tarikh mula atau tamat yang berbeza beserta sebabnya, atau fakta yang tiada atau tersilap. AI menyemaknya berbanding sumber pin ini, mencari yang lebih baik, dan menambah mana-mana halaman yang menyokong anda. Sumber pin itu sendiri tetap paling diambil kira. Gambar yang menunjukkan sesuatu yang lain, atau menunjukkannya dengan buruk, turut dilihat, dan dialihkan ke bawah atau diganti.
Tajuk asal: Caverns Solar: 75 MW solar PV, Jackson County, Florida
Power generation75 MW · 75 MW electrical generation nameplate in September 2026 preliminary planned inventory; not operating output. Operation forecast 2029-12. Scope: CVSO. Annual output is not reported by this inventory; no annual energy inferred. · source