Entri pertama sentiasa sumber pin. Keyakinan keseluruhan ialah purata berpemberat bagi sejauh mana setiap rujukan menyokong masa mula dan tamat yang digunakan di atas; sesebuah rujukan diambil kira separuh kurang bagi setiap 180 hari lebih lama daripada yang terbaharu.
Tarikh yang disimpan ialah anggaran penjejakan atau penanda trajektori kapasiti, bukan hari pembukaan tepat yang disahkan. Status pembinaan mengikut skop fizikal bertarikh yang dinyatakan; tiada penyempurnaan disimpulkan daripada sasaran yang telah berlalu.
Construction research 2026-10-24: Epoch’s[1] 2026-06-17 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “foundations being laid out for Building 2” Dated observation 2026-06-17; future trajectory rows and modeled costs are distinguished from this physical milestone.
Ada yang tertinggal atau salah? Nyatakan dengan kata-kata anda sendiri: pautan yang menyokong pin ini, tarikh mula atau tamat yang berbeza beserta sebabnya, atau fakta yang tiada atau tersilap. AI menyemaknya berbanding sumber pin ini, mencari yang lebih baik, dan menambah mana-mana halaman yang menyokong anda. Sumber pin itu sendiri tetap paling diambil kira. Gambar yang menunjukkan sesuatu yang lain, atau menunjukkannya dengan buruk, turut dilihat, dan dialihkan ke bawah atau diganti.
| Building 1 appears externally complete and likely Ready for Service, with all cooling/roofing/generators in place, but we're not labeling it operational yet due to visible surrounding yard/constructio |
| 2026-08-30 | Building 1 operational at full capacity. This is based on "Phase I", which is [expected](https://investor.galaxy.com/news/news-details/2025/Galaxy-Announces-Third-Quarter-2025-Financial-Results/defaul |
|---|
| 2028-01-01 | Building 2 and 3 are operational at full capacity. This corresponds to "Phase II", which is [expected](https://investor.galaxy.com/news/news-details/2025/Galaxy-Announces-Third-Quarter-2025-Financial- |
|---|
| 2029-01-01 | Building 4 operational at full capacity. This corresponds to "Phase III", which is [expected](https://investor.galaxy.com/news/news-details/2025/Galaxy-Announces-Third-Quarter-2025-Financial-Results/d |
|---|
Epoch AI satellite-imagery notes, in date order. · sumber
Physical-stage observation dated 2026-06-17. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“foundations being laid out for Building 2”
Epoch’s dated 2026-06-17 assessment: foundations being laid out for Building 2 Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“foundations being laid out for Building 2”
Epoch estimates AI hardware: Nvidia B200 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Nvidia B200 chips.”
Epoch dated observation: The former crypto mining Helios site begins converting the first…
“The former crypto mining Helios site begins converting the first building and expanding, with land cleared for additional buildings.”
Epoch assessment: Building 1 appears externally complete and likely Ready for Service, with all…
“Building 1 appears externally complete and likely Ready for Service, with all cooling/roofing/generators in place, but we're not labeling it operational yet due to visible surrounding yard/construction work.”
Epoch dated observation: Building 1 operational at full capacity.
“Building 1 operational at full capacity.”
Tajuk asal: Coreweave Helios AI Data Center Buildout
Coreweave Helios di Afton, Texas, Amerika Syarikat ialah kampus pusat data AI sempadan yang dikendalikan oleh CoreWeave / OpenAI yang mencapai 528 MW kapasiti kuasa dan 638,207 pemecut AI setara H100. Helios dipasang semula daripada bekas tapak perlombongan kripto yang dimiliki oleh Galaxy, yang mempunyai kapasiti tambahan 2.7 GW dalam kajian, walaupun tidak dijangka sebelum 2029.
Dokumen pemerhatian 2026-06-17 Epoch baki pembinaan/pemasangan fizikal untuk binaan dinamakan ini. Dalam Proses tidak menyiapkan bangunan operasi lebih awal atau kapasiti masa hadapan. Kiraan kuasa dan pemecut kekal sebagai anggaran Epoch, bukan penilaian yang diperakui oleh pengendali. Kos modal 2025 dolar yang dimodelkan termasuk perkakasan pengiraan dan bukan belanjawan pembinaan asli sumber.