Entri pertama sentiasa sumber pin. Keyakinan keseluruhan ialah purata berpemberat bagi sejauh mana setiap rujukan menyokong masa mula dan tamat yang digunakan di atas; sesebuah rujukan diambil kira separuh kurang bagi setiap 180 hari lebih lama daripada yang terbaharu.
Mula ialah pembersihan tanah yang diperhatikan oleh Epoch[3][6] (2025-09-27). End ialah unjuran operasi penuh Epoch (2028-12-31), anggaran, bukan tarikh pembangun. Permulaan sedia ada pin (2028-12-28) ialah unjuran, bukan tarikh pecah tanah.
Cited in the project timeline.[1]
Construction research 2026-10-24: Epoch’s[1][6] 2026-03-23 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Steel framing and roofing is underway for Building 1.” Dated observation 2026-03-23; future trajectory rows and modeled costs are distinguished from this physical milestone.
Photo caption and image of Burlington construction May 4, 2026[1]
| 2026-01-04 | Bahagian kecil pembinaan asas bangunan bermula, dan pembersihan tanah nampaknya kebanyakannya telah selesai |
|---|
| 2026-03-23 | Rangka keluli dan bumbung sedang dijalankan untuk Bangunan 1. |
|---|
| 2028-12-31 | Semua bangunan siap, tapak beroperasi sepenuhnya. Alasan kami ialah contoh setakat ini mengambil median 2-2.5 tahun untuk beralih dari pembukaan tanah kepada 1 GW. Ini mencadangkan sekitar 2028-01-01… |
|---|
Nota imej satelit Epoch AI, mengikut urutan tarikh. · sumber
548,950 sq ft, single story, four data halls
“will comprise a single-story 548,950 square foot (51,000 sqm) data center with four data halls.”
1.2 GW planned
“build and operate the previously announced 1.2 GW Stargate data center in Milam County, Texas.”
15 October (2026) / Q4 2028
“All buildings finished, site is fully operational.”
Building 1 steel and roofing; no building confirmed operational
“Steel framing and roofing is underway for Building 1.”
Land clearing begins (Epoch satellite observation)
“Land clearing begins for the site”
Building foundation construction begins
“Small sections of building foundation construction begins, and land clearing appears to be mostly finished”
SB Energy to build and operate the 1.2 GW site; OpenAI and SoftBank invest $1B in SB Energy
“SB Energy will provide the project's powered infrastructure, while SoftBank and OpenAI invest $1 billion in the company to support its growth”
Steel framing and roofing underway for Building 1
“Steel framing and roofing is underway for Building 1.”
TDLR filing for Freebird Phase 1: 548,950 sq ft, four data halls, about $470 million
“The filing discloses the estimated cost of the project at $470 million, with a project completion date of 15 October.”
Phase 1 completion date in TDLR filing (no confirmation of completion published)
“with a project completion date of 15 October.”
Full site fully operational (Epoch projection)
“All buildings finished, site is fully operational.”
Ada yang tertinggal atau salah? Nyatakan dengan kata-kata anda sendiri: pautan yang menyokong pin ini, tarikh mula atau tamat yang berbeza beserta sebabnya, atau fakta yang tiada atau tersilap. AI menyemaknya berbanding sumber pin ini, mencari yang lebih baik, dan menambah mana-mana halaman yang menyokong anda. Sumber pin itu sendiri tetap paling diambil kira. Gambar yang menunjukkan sesuatu yang lain, atau menunjukkannya dengan buruk, turut dilihat, dan dialihkan ke bawah atau diganti.
Tajuk asal: OpenAI Stargate Milam AI Data Center Buildout
Kampus Stargate Milam OpenAI berhampiran Burlington, Texas, ialah pusat data 1.2 GW terancang yang sedang dibina dan dikendalikan oleh SB Energy SoftBank. Imejan satelit menunjukkan rangka keluli dan bumbung di Bangunan 1 menjelang Mac 2026, dan pemfailan negeri untuk Fasa 1 menyenaraikan 548,950 kaki persegi dan kira-kira $470 juta. Epoch AI mengunjurkan operasi penuh menjelang akhir 2028. Tiada bangunan disahkan beroperasi lagi.
Dokumen pemerhatian 2026-03-23 Epoch baki pembinaan/pemasangan fizikal untuk binaan dinamakan ini. Dalam Proses tidak menyiapkan bangunan operasi lebih awal atau kapasiti masa hadapan. Kiraan kuasa dan pemecut kekal sebagai anggaran Epoch, bukan penilaian yang diperakui oleh pengendali. Kos modal 2025 dolar yang dimodelkan termasuk perkakasan pengiraan dan bukan belanjawan pembinaan asli sumber.