Construction research 2026-10-24: Epoch’s[1] 2026-07-30 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “still under construction and not yet energized” Dated observation 2026-07-30; future trajectory rows and modeled costs are distinguished from this physical milestone.
Ada yang tertinggal atau salah? Nyatakan dengan kata-kata anda sendiri: pautan yang menyokong pin ini, tarikh mula atau tamat yang berbeza beserta sebabnya, atau fakta yang tiada atau tersilap. AI menyemaknya berbanding sumber pin ini, mencari yang lebih baik, dan menambah mana-mana halaman yang menyokong anda. Sumber pin itu sendiri tetap paling diambil kira. Gambar yang menunjukkan sesuatu yang lain, atau menunjukkannya dengan buruk, turut dilihat, dan dialihkan ke bawah atau diganti.
| 2027-04-30 | Bangunan 1 Fasa II beroperasi: 207 MW jumlah IT kritikal (300 MW kasar). Fasa II menambah IT kritikal 39 MW (lihat [Cipher 2025-11-20 PR](https://www.globenewswire.com/news-release/2025/11/20/3191801… |
|---|
Nota imej satelit Epoch AI, mengikut urutan tarikh. · sumber
Physical-stage observation dated 2026-07-30. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“still under construction and not yet energized”
Epoch’s dated 2026-07-30 assessment: still under construction and not yet energized Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“still under construction and not yet energized”
AI data-center compute infrastructure. Hardware inventory remains unpublished or not verified in this project assessment.
“AI data center”
Epoch dated observation: Site grading and civil works begin.
“Site grading and civil works begin.”
Epoch dated observation: Building 1 shell is complete, with rooftop units installed, and most…
“Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north.”
Tajuk asal: Anthropic Barber Lake AI Data Center Buildout
Anthropic Barber Lake di Colorado City, Texas, Amerika Syarikat ialah kampus pusat data AI sempadan yang dikendalikan oleh Cipher Mining / Anthropic yang mencapai 207 MW kapasiti kuasa dan 288,530 pemecut AI setara H100. Barber Lake menjalankan TPU Google dan bukannya GPU NVIDIA: Google membekalkan cip dan membantu membiayai pembinaan, mengambil pegangan ekuiti dalam pembangun supaya silikonnya boleh digunakan untuk Anthropic melalui Fluidstack.
Dokumen pemerhatian 2026-07-30 Epoch baki pembinaan/pemasangan fizikal untuk binaan dinamakan ini. Dalam Proses tidak menyiapkan bangunan operasi lebih awal atau kapasiti masa hadapan. Kiraan kuasa dan pemecut kekal sebagai anggaran Epoch, bukan penilaian yang diperakui oleh pengendali. Kos modal 2025 dolar yang dimodelkan termasuk perkakasan pengiraan dan bukan belanjawan pembinaan asli sumber.