Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
| Date | Observed status |
|---|---|
| 2023-01-01 | Land clearing begins, with the east campus being the first of the three. Land clearing begins for the other two campuses months after. |
| 2025-01-01 | The first building is operational. On the north campus, building 4 is operational assuming a 3-month fit-out post structural completion. |
| 2025-03-01 | Three buildings are operational. On the west campus, building 1 is operational, and on the east campus, building 7 is operational. The second building on the east campus has installed generators, but |
| 2025-11-01 | Four buildings are operational. On the west campus, building 2 is operational assuming a 3-month fit-out post structural completion. |
| 2026-01-24 | Four buildings are operational in total. A fifth building, building 5 on the north campus, is finishing installing roofside cooling. Another building on the east campus is complete but does not have s |
| 2026-06-01 | Four buildings are operational. On the north campus, building 5 is nearing structural completion but still has roofing and cooling remaining. |
| 2026-08-06 | On the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars. Building 6, a much larger building across the pond, should finish construction in |
| 2026-11-01 | Five buildings are operational. On the north campus, building 5 is operational assuming a 3-month fit-out post structural completion. |
| 2026-12-31 | Six buildings are operational. On the north campus, building 6, the larger building, is operational assuming a 3-month fit-out if it is structurally complete in September. We assume Building 6 is abou |
| 2027-12-01 | All eight AI buildings are operational. Buildings 3 and 9 are assumed to be 1.25x the power and compute of buildings 1 and 7 based on the sizing of the backup generator enclosures; building 8 is exclu |
Epoch AI satellite-imagery notes, in date order. · sumber
Dalam pembinaan
Digital infrastructure: AI data-center campus buildout · Disemak 2026-10-30
Hanya peringkat yang dilaporkan diserlahkan. Angka dan tarikh membezakan rancangan daripada hasil dibuktikan.
Epoch’s current campus estimate: 157 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 157 MW”
Physical-stage observation dated 2026-08-06. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“building 9 is under construction”
Epoch’s dated 2026-08-06 assessment: building 9 is under construction Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“building 9 is under construction”
Epoch estimates AI hardware: Huawei Ascend 910C chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Huawei Ascend 910C chips.”
Epoch dated observation: Land clearing begins, with the east campus being the first of the three.
“Land clearing begins, with the east campus being the first of the three.”
Epoch dated observation: On the north campus, building 5 is structurally complete but not…
“On the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars.”
Foto daripada pembaca, berasingan daripada media bersumber pin. Nilaikan apa yang anda makan atau lihat, dan pada pin restoran, tag hidangan terus pada foto anda.
Entri pertama sentiasa sumber pin. Keyakinan keseluruhan ialah purata berpemberat bagi sejauh mana setiap rujukan menyokong masa mula dan tamat yang digunakan di atas; sesebuah rujukan diambil kira separuh kurang bagi setiap 180 hari lebih lama daripada yang terbaharu.
Tarikh yang disimpan ialah anggaran penjejakan atau penanda trajektori kapasiti, bukan hari pembukaan tepat yang disahkan. Status pembinaan mengikut skop fizikal bertarikh yang dinyatakan; tiada penyempurnaan disimpulkan daripada sasaran yang telah berlalu.
Construction research 2026-10-24: Epoch’s[1] 2026-08-06 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “building 9 is under construction” Dated observation 2026-08-06; future trajectory rows and modeled costs are distinguished from this physical milestone.
Ada yang tertinggal atau salah? Nyatakan dengan kata-kata anda sendiri: pautan yang menyokong pin ini, tarikh mula atau tamat yang berbeza beserta sebabnya, atau fakta yang tiada atau tersilap. AI menyemaknya berbanding sumber pin ini, mencari yang lebih baik, dan menambah mana-mana halaman yang menyokong anda. Sumber pin itu sendiri tetap paling diambil kira. Gambar yang menunjukkan sesuatu yang lain, atau menunjukkannya dengan buruk, turut dilihat, dan dialihkan ke bawah atau diganti.
Tajuk asal: Huawei Wuhu AI Data Center Buildout
Huawei Wuhu di Wuhu, Anhui, China ialah kampus pusat data AI sempadan yang dikendalikan oleh Huawei yang mencapai 457 MW kapasiti kuasa dan 221,924 pemecut AI setara H100. 0
Dokumen pemerhatian 2026-08-06 Epoch baki pembinaan/pemasangan fizikal untuk binaan dinamakan ini. Dalam Proses tidak menyiapkan bangunan operasi lebih awal atau kapasiti masa hadapan. Kiraan kuasa dan pemecut kekal sebagai anggaran Epoch, bukan penilaian yang diperakui oleh pengendali. Kos modal 2025 dolar yang dimodelkan termasuk perkakasan pengiraan dan bukan belanjawan pembinaan asli sumber.