Digital infrastructure: AI data-center campus buildout · Disemak 2026-10-30
Hanya peringkat yang dilaporkan diserlahkan. Angka dan tarikh membezakan rancangan daripada hasil dibuktikan.
Epoch’s current campus estimate: 0 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 0 MW”
Physical-stage observation dated 2026-07-30. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Construction on Buildings 3 and 4 has begun”
Epoch’s dated 2026-07-30 assessment: Construction on Buildings 3 and 4 has begun Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Construction on Buildings 3 and 4 has begun”
AI data-center compute infrastructure. Hardware inventory remains unpublished or not verified in this project assessment.
“AI data center”
Epoch dated observation: Land clearing begins.
“Land clearing begins.”
Epoch dated observation: Roofs of Buildings 1 and 2 are more than halfway complete.
“Roofs of Buildings 1 and 2 are more than halfway complete.”
Foto daripada pembaca, berasingan daripada media bersumber pin. Nilaikan apa yang anda makan atau lihat, dan pada pin restoran, tag hidangan terus pada foto anda.
Entri pertama sentiasa sumber pin. Keyakinan keseluruhan ialah purata berpemberat bagi sejauh mana setiap rujukan menyokong masa mula dan tamat yang digunakan di atas; sesebuah rujukan diambil kira separuh kurang bagi setiap 180 hari lebih lama daripada yang terbaharu.
Tarikh yang disimpan ialah anggaran penjejakan atau penanda trajektori kapasiti, bukan hari pembukaan tepat yang disahkan. Status pembinaan mengikut skop fizikal bertarikh yang dinyatakan; tiada penyempurnaan disimpulkan daripada sasaran yang telah berlalu.
Construction research 2026-10-24: Epoch’s[1] 2026-07-30 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Construction on Buildings 3 and 4 has begun” Dated observation 2026-07-30; future trajectory rows and modeled costs are distinguished from this physical milestone.
Ada yang tertinggal atau salah? Nyatakan dengan kata-kata anda sendiri: pautan yang menyokong pin ini, tarikh mula atau tamat yang berbeza beserta sebabnya, atau fakta yang tiada atau tersilap. AI menyemaknya berbanding sumber pin ini, mencari yang lebih baik, dan menambah mana-mana halaman yang menyokong anda. Sumber pin itu sendiri tetap paling diambil kira. Gambar yang menunjukkan sesuatu yang lain, atau menunjukkannya dengan buruk, turut dilihat, dan dialihkan ke bawah atau diganti.
Tajuk asal: Meta Bowling Green AI Data Center Buildout
Meta Bowling Green di Bowling Green, Ohio, Amerika Syarikat ialah kampus pusat data AI sempadan yang dikendalikan oleh Meta yang mencapai 422 MW kapasiti kuasa dan 855,159 pemecut AI setara H100. 0
Dokumen pemerhatian 2026-07-30 Epoch baki pembinaan/pemasangan fizikal untuk binaan dinamakan ini. Dalam Proses tidak menyiapkan bangunan operasi lebih awal atau kapasiti masa hadapan. Kiraan kuasa dan pemecut kekal sebagai anggaran Epoch, bukan penilaian yang diperakui oleh pengendali. Kos modal 2025 dolar yang dimodelkan termasuk perkakasan pengiraan dan bukan belanjawan pembinaan asli sumber.