Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
| Date | Observed status |
|---|---|
| 2024-11-18 | Core Scientific, CoreWeave, and Port Muskogee publicly announce groundbreaking for the 100 MW Muskogee HPC data center. Core Scientific [says](https://investors.corescientific.com/news-events/press-re |
| 2026-04-09 | Based on satellite imagery, Building 1 looks mostly complete, but the site still appears to be in construction or commissioning. Not much progress has happened in the past 4 months, and a Q2 2026 fini |
| 2026-06-13 | Based on satellite imagery, Building 1 has completed construction, with adjacent land cleared for what we're assuming will have power substations/generators. We can assume Building 1 is not operationa |
| 2026-12-31 | Estimating building 1 is operational by the end of the year, judging from the building currently completed, the completed power substation to the southwest. The surrounding yard work/construction will |
| 2027-12-31 | Core Scientific expects initial delivery of the second, unleased 82.5 MW Muskogee building in Q4 2027. Not signed to have CoreWeave GPUs as of yet, but may change in the future. Source: https://www.se |
Epoch AI satellite-imagery notes, in date order. · sumber
Dalam pembinaan
Digital infrastructure: AI data-center campus buildout · Disemak 2026-10-30
Hanya peringkat yang dilaporkan diserlahkan. Angka dan tarikh membezakan rancangan daripada hasil dibuktikan.
Epoch’s current campus estimate: 0 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 0 MW”
Physical-stage observation dated 2026-06-13. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“all the yard work directly surrounding it”
Epoch’s dated 2026-06-13 assessment: all the yard work directly surrounding it Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“all the yard work directly surrounding it”
AI data-center compute infrastructure. Hardware inventory remains unpublished or not verified in this project assessment.
“AI data center”
Epoch dated observation: Core Scientific, CoreWeave, and Port Muskogee publicly announce…
“Core Scientific, CoreWeave, and Port Muskogee publicly announce groundbreaking for the 100 MW Muskogee HPC data center.”
Epoch assessment: Based on satellite imagery, Building 1 has completed construction, with…
“Based on satellite imagery, Building 1 has completed construction, with adjacent land cleared for what we're assuming will have power substations/generators.”
Foto daripada pembaca, berasingan daripada media bersumber pin. Nilaikan apa yang anda makan atau lihat, dan pada pin restoran, tag hidangan terus pada foto anda.
Entri pertama sentiasa sumber pin. Keyakinan keseluruhan ialah purata berpemberat bagi sejauh mana setiap rujukan menyokong masa mula dan tamat yang digunakan di atas; sesebuah rujukan diambil kira separuh kurang bagi setiap 180 hari lebih lama daripada yang terbaharu.
Tarikh yang disimpan ialah anggaran penjejakan atau penanda trajektori kapasiti, bukan hari pembukaan tepat yang disahkan. Status pembinaan mengikut skop fizikal bertarikh yang dinyatakan; tiada penyempurnaan disimpulkan daripada sasaran yang telah berlalu.
Construction research 2026-10-24: Epoch’s[1] 2026-06-13 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “all the yard work directly surrounding it” Dated observation 2026-06-13; future trajectory rows and modeled costs are distinguished from this physical milestone.
Ada yang tertinggal atau salah? Nyatakan dengan kata-kata anda sendiri: pautan yang menyokong pin ini, tarikh mula atau tamat yang berbeza beserta sebabnya, atau fakta yang tiada atau tersilap. AI menyemaknya berbanding sumber pin ini, mencari yang lebih baik, dan menambah mana-mana halaman yang menyokong anda. Sumber pin itu sendiri tetap paling diambil kira. Gambar yang menunjukkan sesuatu yang lain, atau menunjukkannya dengan buruk, turut dilihat, dan dialihkan ke bawah atau diganti.
Tajuk asal: CoreWeave Muskogee OK AI Data Center Buildout
Dokumen pemerhatian 2026-06-13 Epoch baki pembinaan/pemasangan fizikal untuk binaan yang dinamakan ini. Dalam Proses tidak menyiapkan bangunan operasi lebih awal atau kapasiti masa hadapan. Kiraan kuasa dan pemecut kekal sebagai anggaran Epoch, bukan penilaian yang diperakui oleh pengendali. Kos modal 2025 dolar yang dimodelkan termasuk perkakasan pengiraan dan bukan belanjawan pembinaan asli sumber.
Latihan AI sempadan hiperskala dan kampus inferens yang dijejaki oleh Epoch AI dengan jejak satelit beranotasi (6 bahagian fizikal).