Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · sumber
| Date | Observed status |
|---|---|
| 2022-07-01 | Land clearing begins for Buildings 5-9 (eastern campus). |
| 2024-12-01 | Buildings 5-9 (eastern campus) operational. [New Albany’s Dec. 2024 report](https://newalbanyohio.org/wp-content/uploads/2025/01/CD-2024-12.pdf) lists AWS partial occupancy for 5 buildings at the east |
| 2026-03-12 | Middle campus Buildings 10, 12, 13, and 14 appear complete/likely operational. Building 11 is still installing backup generators, so it is not counted as operational. Based on satellite imagery, north |
| 2026-05-18 | Satellite imagery shows Building 1 in the northern campus still appears structurally finished, with no visible change from the prior two months, but we're still not counting it operational due to visi |
| 2027-07-01 | Expected operational date for the remaining tracked buildings (11, and 1-4) across the three campuses. This estimate is based on the previous buildings taking roughly 1.5 years from steel framing to c |
Epoch AI satellite-imagery notes, in date order. · sumber
Dalam pembinaan
Digital infrastructure: AI data-center campus buildout · Disemak 2026-10-30
Hanya peringkat yang dilaporkan diserlahkan. Angka dan tarikh membezakan rancangan daripada hasil dibuktikan.
Epoch’s current campus estimate: 213 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 213 MW”
Physical-stage observation dated 2026-05-18. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“generators/cooling equipment being installed”
Epoch’s dated 2026-05-18 assessment: generators/cooling equipment being installed Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“generators/cooling equipment being installed”
Epoch estimates AI hardware: Amazon Trainium2, Nvidia H100, Nvidia H200, and Nvidia B200 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Amazon Trainium2, Nvidia H100, Nvidia H200, and Nvidia B200 chips.”
Epoch dated observation: Land clearing begins for Buildings 5-9 (eastern campus).
“Land clearing begins for Buildings 5-9 (eastern campus).”
Epoch assessment: Satellite imagery shows Building 1 in the northern campus still appears…
“Satellite imagery shows Building 1 in the northern campus still appears structurally finished, with no visible change from the prior two months, but we're still not counting it operational due to visible construction work around the perimeter.”
Foto daripada pembaca, berasingan daripada media bersumber pin. Nilaikan apa yang anda makan atau lihat, dan pada pin restoran, tag hidangan terus pada foto anda.
Entri pertama sentiasa sumber pin. Keyakinan keseluruhan ialah purata berpemberat bagi sejauh mana setiap rujukan menyokong masa mula dan tamat yang digunakan di atas; sesebuah rujukan diambil kira separuh kurang bagi setiap 180 hari lebih lama daripada yang terbaharu.
Tarikh yang disimpan ialah anggaran penjejakan atau penanda trajektori kapasiti, bukan hari pembukaan tepat yang disahkan. Status pembinaan mengikut skop fizikal bertarikh yang dinyatakan; tiada penyempurnaan disimpulkan daripada sasaran yang telah berlalu.
Construction research 2026-10-24: Epoch’s[1] 2026-05-18 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “generators/cooling equipment being installed” Dated observation 2026-05-18; future trajectory rows and modeled costs are distinguished from this physical milestone.
Ada yang tertinggal atau salah? Nyatakan dengan kata-kata anda sendiri: pautan yang menyokong pin ini, tarikh mula atau tamat yang berbeza beserta sebabnya, atau fakta yang tiada atau tersilap. AI menyemaknya berbanding sumber pin ini, mencari yang lebih baik, dan menambah mana-mana halaman yang menyokong anda. Sumber pin itu sendiri tetap paling diambil kira. Gambar yang menunjukkan sesuatu yang lain, atau menunjukkannya dengan buruk, turut dilihat, dan dialihkan ke bawah atau diganti.
Tajuk asal: AWS New Albany AI Data Center Buildout
Dokumen pemerhatian 2026-05-18 Epoch baki pembinaan/pemasangan fizikal untuk binaan dinamakan ini. Dalam Proses tidak menyiapkan bangunan operasi lebih awal atau kapasiti masa hadapan. Kiraan kuasa dan pemecut kekal sebagai anggaran Epoch, bukan penilaian yang diperakui oleh pengendali. Kos modal 2025 dolar yang dimodelkan termasuk perkakasan pengiraan dan bukan belanjawan pembinaan asli sumber.
Latihan AI sempadan hiperskala dan kampus inferens yang dijejaki oleh Epoch AI dengan jejak satelit beranotasi (31 bahagian fizikal).