Halaman projek LAWA[2][3][4]: “Penyiapan Jalan Masuk dijangka pada Mei 2028. Penyiapan projek dijangka pertengahan 2030”; satu bulan mengambil hari terakhirnya.
A $289 million FAA Airport Infrastructure Grant supports the ongoing construction of the ingress roadways; LAWA[1][3][4] anticipates the ingress roadways ahead of the 2028 Summer Olympics and full completion of the egress roadways by 2030.
First major Sepulveda Boulevard closures on July 13-19, 2026, after the last World Cup quarterfinal at SoFi Stadium, to build a new pedestrian bridge at Century and Sepulveda as part of the ATMP Roadway Improvements Project.[1]
The pylon ring came down in January 2026 for the roadway project; reimagined pylons return upon completion of roadway improvements by 2030.[1]
Ada yang tertinggal atau salah? Nyatakan dengan kata-kata anda sendiri: pautan yang menyokong pin ini, tarikh mula atau tamat yang berbeza beserta sebabnya, atau fakta yang tiada atau tersilap. AI menyemaknya berbanding sumber pin ini, mencari yang lebih baik, dan menambah mana-mana halaman yang menyokong anda. Sumber pin itu sendiri tetap paling diambil kira. Gambar yang menunjukkan sesuatu yang lain, atau menunjukkannya dengan buruk, turut dilihat, dan dialihkan ke bawah atau diganti.