LG&E/KU’s current Mill Creek 5 page states a 645 MW nameplate rating, $902 million cost, construction underway and estimated completion in 2027. Its 2024 groundbreaking release used 640 MW; the current page is used for the primary output rating. EIA’s separate 740 MW figure is retained as inventory context, not extra generating capacity.
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Operator source page; original image.
Disuntingoleh @ThePinGang
Sebelum
LG&E/KU’s current Mill Creek 5 page states a 645 MW nameplate rating, $902 million cost, construction underway and estimated completion in 2027. Its 2024 groundbreaking release used 640 MW; the current page is used for the primary output rating. EIA’s separate 740 MW figure is retained as inventory context, not extra generating capacity.
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Disuntingoleh @ThePinGang
Sebelum
Sebelum
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels.
EIA August 2026 generator inventory, plant ID 1364: Mill Creek (KY), Jefferson County, KY. Included 1 new/recent generating units with a summed nameplate rating of 740 MW.
EIA reports operation at month/year precision. The date is the last day of the earliest reported operation month/year, an estimated display boundary, not an exact opening day. Different units may have later dates. Future dates are operator-reported plans, not guarantees.
Coordinates are the EIA-reported plant point, not a verified entrance. New units at existing plants are included; the total excludes older units and battery/pumped storage. Capacity is a power rating, not annual energy output. Status was reported in August and may have changed since.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Entri pertama sentiasa sumber pin. Keyakinan keseluruhan ialah purata berpemberat bagi sejauh mana setiap rujukan menyokong masa mula dan tamat yang digunakan di atas; sesebuah rujukan diambil kira separuh kurang bagi setiap 180 hari lebih lama daripada yang terbaharu.
Documented physical milestone or dated progress/reporting marker. Period-end dates represent only the reported month/quarter; they do not invent an exact operation date. Source estimates are labelled and not treated as confirmed future opening dates.
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.[1]
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s[1] August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Ada yang tertinggal atau salah? Nyatakan dengan kata-kata anda sendiri: pautan yang menyokong pin ini, tarikh mula atau tamat yang berbeza beserta sebabnya, atau fakta yang tiada atau tersilap. AI menyemaknya berbanding sumber pin ini, mencari yang lebih baik, dan menambah mana-mana halaman yang menyokong anda. Sumber pin itu sendiri tetap paling diambil kira. Gambar yang menunjukkan sesuatu yang lain, atau menunjukkannya dengan buruk, turut dilihat, dan dialihkan ke bawah atau diganti.
LG&E/KU’s current Mill Creek 5 page states a 645 MW nameplate rating, $902 million cost, construction underway and estimated completion in 2027. Its 2024 groundbreaking release used 640 MW; the current page is used for the primary output rating. EIA’s separate 740 MW figure is retained as inventory context, not extra generating capacity.[2][3]
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.[2]
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.[3]
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Operator source page; original image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Operator source page; original image.