New Cumberland natural-gas plant construction, photographed July 16, 2025. This is the new plant, not the existing coal plant’s control room.[1]
TVA FY2025 Form 10-K publishes $1.8 billion spent and $312 million expected additional spending for the 1,450 MW first replacement combined-cycle plant, as of September 30, 2025. Their sum is approximately $2.112 billion. This explicitly calculated total uses published project components, not technology cost benchmarks. Equipment and prospective expenditure for a second replacement plant are excluded. Cumberland combined-cycle replacement plant: published generating capacity 1450 MW. Operator-reported electric generating capacity; not annual energy production TVA reports this first 1,450 MW plant in construction. Its June 2026 filing reports pre-commercial operation of Cumberland Units 1 and 2 during the fiscal third quarter; this is commissioning, not proof of full commercial operation.[1]
TVA reports pre-commercial operation of Cumberland Units 1 and 2 in April–June 2026.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
TVA FY2025 Form 10-K publishes $1.8 billion spent and $312 million expected additional spending for the 1,450 MW first replacement combined-cycle plant, as of September 30, 2025. Their sum is approximately $2.112 billion. This explicitly calculated total uses published project components, not technology cost benchmarks. Equipment and prospective expenditure for a second replacement plant are excluded.[3][4]
TVA FY2025 Form 10-K publishes $1.8 billion spent and $312 million expected additional spending for the 1,450 MW first replacement combined-cycle plant, as of September 30, 2025. Their sum is approximately $2.112 billion. This explicitly calculated total uses published project components, not technology cost benchmarks. Equipment and prospective expenditure for a second replacement plant are excluded. Cumberland combined-cycle replacement plant: published generating capacity 1450 MW. Operator-reported electric generating capacity; not annual energy production TVA reports this first 1,450 MW plant in construction. Its June 2026 filing reports pre-commercial operation of Cumberland Units 1 and 2 during the fiscal third quarter; this is commissioning, not proof of full commercial operation.[3]
TVA reports pre-commercial operation of Cumberland Units 1 and 2 in April–June 2026.[4]
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
New Cumberland natural-gas plant construction, photographed July 16, 2025. This is the new plant, not the existing coal plant’s control room. Credit: Lee Erwin / Clarksville Now. Source and gallery; original media.