The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
The article states "Work on foundational infrastructure began in April 2026, with groundbreaking scheduled for early 2027", giving the month but not the day. Completion: Washington Commanders[2] release, 11 Aug 2026: "Construction on the new Washington Commanders Stadium is anticipated to begin in spring 2027, with a targeted completion date of spring 2030" (spring read as ending 31 May); DC's OurRFK site: "The new stadium is expected to open in 2030."
The team, which is building the stadium, names the general contractor and gives a targeted completion date of spring 2030 (construction start spring 2027, enabling work since June 2026); DC's OurRFK FAQ agrees on opening in 2030. endDate is the last day of meteorological spring.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
Approximately 65,000 seats in an enclosed facility
“approximately 65,000-seat enclosed facility”
Construction anticipated spring 2027; targeted completion spring 2030
“anticipated to begin in spring 2027, with a targeted completion date of spring 2030.”
Construction joint venture selected
“have selected a joint venture of Clark Construction Group, Mortenson, and Smoot Construction Company of Washington, DC”
Expected completion (year precision; spring target)
“targeted completion date of spring 2030.”
The published cost is $3.8 billion: Projected total cost of the New Stadium at RFK Campus (Commanders contribute $2.7bn, the District $500m for infrastructure per the pin).[1]
Planned design figure · About 65,000 seats; 180-acre campus omitted.