Happened as dated, per the source: "Work began on May 29, 2025, when a groundbreaking ceremony for a temporary terminal on Dyer Avenue between 37th and 39th streets was hosted." Completion: Port Authority release, 27 Apr 2026 (first steel for the Dyer Avenue deck-overs): "Phase 1 will be complete in 2030, when construction of the second phase will begin. Phase 2, including the demolition of the existing terminal and the construction of a new bus terminal in the same location, will be complete in 2035." Cost: ABC7 (15 Oct 2026) and NY1[3][8] (23 Oct 2026) report an $11 billion project; the $10 billion figure was the May 2025 groundbreaking estimate.
Whole replacement programme; Gothamist notes it is a minimum and not fully funded. Pin covers the temporary-terminal groundbreaking, which is part of it; no phase figure found.[1]
Oct 2026: construction under way on an $11 billion terminal, deck-overs, Garcia on the result, completion 2035[1]
Oct 2026: $11 billion project, Lincoln Tunnel ramp removal and rerouting, Phase 1 by end of 2030 and terminal in 2035[1]
Oct 2026: traffic disruptions and Midtown commuter and resident reactions[1]
Approximately 6,000 construction jobs across the replacement project; not operating staffing.
“approximately 6,000 good-paying union construction jobs”
2.1 million sq ft main terminal; separate staging/storage building excluded from that figure.
“2.1 million square-foot main terminal”
18 May 2026 construction-management announcement; not asserted as the first day of physical work.
“provide construction management (CM) services for Phase 1”
900,000 sq ft interim facility transitions into bus staging/storage in later phases.
“900,000-square-foot interim facility”
Federal and city approvals secured
“Record of Decision Issued Today”
Groundbreaking: phase one (Dyer Avenue deck-overs, temporary terminal) begins
“Phase one of the project is now underway”
First steel beams placed for the Dyer Avenue deck-overs
“announced that placement of the first steel beams to support the Dyer Avenue deck overs has begun”
First-phase construction-management appointment reported
“provide construction management (CM) services for Phase 1”
Lincoln Tunnel ramp removal begins; buses rerouted
“Crews have begun removing ramps that carry buses from the Lincoln Tunnel into the 75-year-old terminal”
Estimated: Phase 1 complete
“Phase 1 is expected to be completed by the end of 2030, with the new bus terminal scheduled for completion in 2035.”
Estimated: new bus terminal complete
“Completion is set for 2035.”
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
The existing Port Authority Bus Terminal, the busiest bus terminal in the world by volume, has reached peak-hour capacity, causing congestion and overflow onto local streets, and it has no layover parking, so buses wait on local streets, in lots or in tunnels.
How: Rebuild the terminal on the same site with layover facilities, after first building a temporary terminal on Dyer Avenue.
For: The roughly 225,000 people and 8,000 buses using the terminal on an average weekday.
Planned design figure · 2.1M sq ft main terminal; excludes staging/storage building; 3.5 acres of publicly accessible green space on Port Authority property at project end.