Chuo Shinkansen Maglev Tokyo to Nagoya
- The Chuo Shinkansen is JR Central's 505 km/h maglev, 285.6 km Tokyo (Shinagawa) to Nagoya, about 90% in tunnels, with a 40-minute journey; construction began 17 December 2014[1]
- Cost is over ¥9 trillion (about $82 billion), up from 5.1 trillion yen estimated in 2007[1]
- The original 2027 opening was abandoned: in March 2024 JR Central said it could not project a new date because tunnel work in Shizuoka had not begun[1][3]
- Shizuoka refused permission in June 2020 over Oi River water concerns on about 9 km of tunnel; governor Suzuki, elected May 2024, signed a compensation agreement in January 2026 and the prefecture approved all 28 environmental measures on 26 March 2026[1][3]
- Wikipedia now gives Tokyo-Nagoya as "no earlier than 2035" (JR president said in 2024 not before at least 2034); a July 2026 announcement would allow service as early as 2036[1]
- Nagoya-Osaka moved from as late as 2045 to as early as 2037[1]