Asia Direct Cable Enters Service for PLDT
- PLDT announced the Asia Direct Cable's operational and commercial readiness, completing a 9,988-kilometre fibre system linking the Philippines to Singapore, Hong Kong, Japan, Vietnam, Thailand and China[1]
- PLDT's 20-F says ADC went into service in February 2025 and took the group's total international capacity to about 100 Tbps[2]
- Consortium co-chair China Telecom declared ADC capacity in service on 14 February 2025, two months ahead of schedule[3]
- NEC built the cable, declared ready for service in December 2024, two years late after delays media reports tied mostly to permits; the consortium is China Telecom, China Unicom, National Telecom, PLDT, Singtel, SoftBank, Tata Communications and Viettel[4]
- PLDT spent US$75 million on the Philippine link and landed the shore end at its Nasugbu, Batangas cable station in November 2022[5][6]
- PLDT pitches ADC as the shortest route into its VITRO Sta. Rosa hyperscale data centre and an intra-Asia complement to the trans-Pacific Jupiter cable[1]
Notable features
- Length: 9,988 km, with landings at Nasugbu (Philippines), Tuas (Singapore), Chung Hom Kok (Hong Kong), Maruyama (Japan), Quy Nhon (Vietnam), Sri Racha (Thailand) and Shantou (China)[1][6]
- Design capacity: more than 160 Tbps over eight fibre pairs[4]
- Transmission: at least 200G DWDM per wavelength[6]
- Adds more than 100 Tbps to PLDT's international capacity[1]
References 690% CONFIDENCE
The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
- [1]90%main.pldt.com/article/asia-direct-cable-boosts-pldts-international-connectivity-hyperscalers-multinationalmain.pldt.com· Posted Sep 24, 2026· Starts Feb 11, 2025 ✓· 57% of score
PLDT's[5][6] release of 11 February 2025 announces the cable 'marking its operational and commercial readiness', and PLDT's 20-F for 2025 (reference 1) states 'In February 2025, ADC went into service'.
- [2]92%PLDT Form 20-F for fiscal year 2025 (SEC)sec.gov· Published Apr 27, 2026· 32% of score
PLDT's[1][5][6] annual report on Form 20-F states 'In February 2025, ADC went into service' and that ADC 'reached operational and commercial readiness in the first quarter of 2025', lifting total international capacity to about 100 Tbps.
- [3]85%China Telecom's Asia Direct Cable (ADC) Capacity Enters Service Ahead of Scheduleprnewswire.com· Published Feb 14, 2025· 6% of score
Consortium co-chair China Telecom announced on 14 February 2025 that ADC capacity was officially in service two months ahead of plan, after the wet segment's ready-for-service in late 2024.[1]
- [4]80%ADC cable ready for service with 160 Tbps of new intra-Asia capacitydevelopingtelecoms.com· Published Dec 20, 2024· 5% of score
Reports NEC finished building the 9,400 km, eight-fibre-pair ADC, declared ready for service in December 2024 and owned by a consortium that includes PLDT[1][5][6].
- [5]85%PLDT Bolsters PH Digital Advantage, Completes Landing of Asia Direct Cable System PH Segmentmain.pldt.com· Published Nov 25, 2022· 0% of score
PLDT's[1][6] release on landing the shore-end segment at its Nasugbu, Batangas cable station, which also hosts SEA-ME-WE3 and APCN-2.
Suggest a correction
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.