Moved, per The Frisc: "the SFPUC[2] has pushed back the start date another five-plus years to the end of 2029"; the SFPUC's project page: "the start date for major construction on the Ocean Beach Climate Change Adaptation Project is now anticipated for late 2029".
The SFPUC's own project page: major construction 'now anticipated for late 2029', about four years long, with the project elements, phasing and parking changes.
Coastal Commission's unanimous approval of the $175 million project, the 3,200-foot buried seawall and the Lake Merced Tunnel it protects.[1]
The earlier promise: the Great Highway Extension between Sloat and Skyline to close to cars by early 2026, with Sloat Plaza and the trail.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.