Section 2 groundbreaking was 23 February 2018. Metro’s[3][5][6] November 19, 2026 staff report forecasts substantial completion in Fall 2027, superseding its earlier Spring 2027 milestone; November 30 is an estimated season-end marker, not a promised opening day. Passenger service timing remains unconfirmed.
Primary staff report states substantial completion shifts Spring to Fall 2027; existing $2,574,969,299 LOP and requested $296m increase, not an adopted action.[1]
Metro's[5][6] fact sheet: Section 2 is 2.59 miles with Beverly Dr and Century City stations, operations Spring 2027; life-of-project budget for all three sections $9.7 billion.
Section 2 groundbreaking February 23, 2018; tunneling completed April 2, 2024; Section 1 opened May 8, 2026; Sections 2 and 3 listed for 2027.[1]
Metro's[3][6] forecasted schedule table: Section 2 construction 2018-2026, operations Spring 2027; Section 3 operations Fall 2027; Section 1 opened May 8, 2026.
2.6 miles (4.2 km) to Century City
“which will extend trackage 2.6 miles (4.2 km) further to Century City”
Fall 2027, shifted from Spring 2027
“The revised forecast for substantial completion shifts from Spring 2027 to Fall 2027.”
Section 1 opened May 8, 2026; Section 2 under construction
“Construction was completed in early 2026, and Section 1 opened on May 8, 2026.”
Section 2 official groundbreaking ceremony
“the official Section 2 groundbreaking ceremony took place on February 23, 2018”
Section 1 opened
“Section 1 opened on May 8, 2026”
Section 2 substantial completion forecast; not passenger opening
“The revised forecast for substantial completion shifts from Spring 2027 to Fall 2027.”
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
Metro’s November 19, 2026 staff report lists the existing Section 2 life-of-project budget as US$2,574,969,299 and requests another US$296 million, taking the proposed total to US$2,870,969,299. The agenda record has no final action posted, so the higher amount is a request, not a verified approved budget. The report says substantial completion has shifted from spring to fall 2027 following settlement of contractor claims; substantial completion is distinct from passenger service.[2]
The map point is an estimated station-area anchor at Constellation Boulevard and Avenue of the Stars, rather than a verified entrance.