Sydney Western Harbour Tunnel Set to Open
Construction research — October 24, 2026
NSW’s August 11, 2026 release confirms both tunnel-boring machines working and mechanical/electrical fit-out progressing, with full opening targeted for 2028. Delivery engineer ADG reports A$7.4 billion for the Western Harbour Tunnel project, excluding the separate Warringah Freeway upgrade.
- Second giant Tunnel Boring Machine begins excavating for the Western Harbour Tunnel: With both tunnel boring machines now in action, we are making strong progress on the final stage of excavation[3]
- Gantry Crane Design for Underground TBM — ADG: The Western Harbour Tunnel, a $7.4 billion city-shaping project[2]
Earlier pin evidence
- The 6.5 km Western Harbour Tunnel under Sydney Harbour remains on track to open in 2028, per an 11 August 2026 NSW Government release[3][4]
- Second TBM Barangaroo launched from Birchgrove Oval, joining Patyegarang, which started the month before; together they dig the final 1.5 km of twin tunnels between Birchgrove and Waverton[3][4]
- Each TBM is 15.7 m in diameter and 4,350 tonnes, the largest assembled underground in the Southern Hemisphere, working around the clock up to 50 m below sea level and installing about 13,000 precast segments[3][4]
- Expected traffic cuts are 35% on the Western Distributor, 20% in the Sydney Harbour Tunnel and 17% on the Harbour Bridge[3][4]
- The Berry St on-ramp in North Sydney is nearing completion, with mechanical and electrical fit-out under way[3]