August 25, 2026 reporting citing CDA’s August 21 bond prospectus places the Global Terminal in 2034 and southern Concourse E around 2034. Retains December 31, 2034 as an estimated terminal-program year anchor, not an exact opening day or guarantee for every optional/later scope. Concourse D is separately targeted for late 2028.
Construction research 2026-10-24: O’Hare’s terminal program remains In Progress: Concourse D construction is active while the Global Terminal and Concourse E remain future scopes. August 25, 2026 reporting gives US$12.5 billion for the redevelopment, superseding the saved rounded US$12 billion; narrower ORDNext approvals and the Concourse D contract have different cost bases/scopes. The estimated 2034 year anchor is retained for the reported Global Terminal/core terminal horizon, not an exact opening day or a guarantee every later optional package finishes together. Source quote: “Broke ground on foundation work for Satellite Concourse 1” Chicago Department of Aviation, 2025 Key Results; primary evidence of actual construction within the program.[1]
Construction research 2026-10-24: O’Hare’s terminal program remains In Progress: Concourse D construction is active while the Global Terminal and Concourse E remain future scopes. August 25, 2026 reporting gives US$12.5 billion for the redevelopment, superseding the saved rounded US$12 billion; narrower ORDNext approvals and the Concourse D contract have different cost bases/scopes. The estimated 2034 year anchor is retained for the reported Global Terminal/core terminal horizon, not an exact opening day or a guarantee every later optional package finishes together. Source quote: “$12.5 billion” Published narrative covers full redevelopment and cites August 21 CDA bond prospectus for schedules; Global Terminal 2034, Concourse E north 2030 and south around 2034.[1]
Broader ORDNext completion target
“2034”
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
O’Hare’s terminal program remains In Progress: Concourse D construction is active while the Global Terminal and Concourse E remain future scopes. August 25, 2026 reporting gives US$12.5 billion for the redevelopment, superseding the saved rounded US$12 billion; narrower ORDNext approvals and the Concourse D contract have different cost bases/scopes. The estimated 2034 year anchor is retained for the reported Global Terminal/core terminal horizon, not an exact opening day or a guarantee every later optional package finishes together.