Atmosphere and energy developers are constructing the 2.2B USD, 300 MW critical IT load data center campus repurposing markets 360 MW in development at Dickerson. Its county-filed 2026 conditional-use amendment covers an approximately 110-acre parcel inside a 758-acre parent tract, differing from the former Dickerson power plant site in Montgomery County, Maryland, on PJM 230/500 kV lines.operator website’s 170-acre marketing scope. This is a proposed campus, not verified 300 MW energized IT.
The Montgomery County Council and Maryland PSC reviewed master redevelopment plans for the 300 MW Dickerson Digital Campus. Features 300 MW of critical power capacity across 2.0 million square feet of powered shell and high-density computing space. Represents an estimated 2.2 billion USD brownfield redevelopment repurposing retired coal generation switchyards into digital infrastructure. Directly interconnects to the Potomac Electric Power Company (PEPCO) / PJM 230 kV and 500 kV extra-high-voltage network. Engineered to expand the Northern Virginia and Maryland data center ecosystem with ultra-fast fiber to Ashburn. Timeline: planned facility targeting commercial operation in November 2027 (estimated) aligned with utility substation energization and phased campus delivery.application describes five data-center buildings and cooling using Potomac River water, with well water for domestic use. Operator-wide air/liquid cooling options do not establish a built waterless system. The adjacent proposed 2,000 MWh BESS is separate, not operating data-center capacity. County statement records original conditional-use decisions November 20 and December 5, 2024, with an amendment sought in 2026. No $2.2B campus budget or operating certificate is established. Timeline: November 30, 2027 remains an unverified legacy COD; neither opened primary source supplies a definite first-service date. Exact marker and final approved boundary remain open.
Editadopor @ThePinGang
… data center ecosystem with ultra-fast fiber to Ashburn. Timeline: planned facility targeting commercial operation in November 2027 (estimated) aligned with utility substation energization and phased campus delivery.
Fotos de leitores, separadas das mídias com fontes do pin. Avalie o que você comeu ou viu e, em um pin de restaurante, marque os pratos direto na sua foto.
A primeira entrada é sempre a fonte do pin. A confiança geral é uma média ponderada de quanto cada referência sustenta os horários de início e fim usados acima; uma referência conta metade a cada 180 dias a mais em relação à mais recente.
Legado não verificado COD de novembro de 2027; os materiais atuais do operador/de uso condicional estabelecem o desenvolvimento futuro, não esta data de entrega.
Falta algo ou há um erro? Diga com suas palavras: um link que sustente este pin, uma data de início ou fim diferente e por quê, ou um fato que falta ou está errado. A IA confere isso com as fontes do pin, procura outras melhores e adiciona qualquer página que dê razão a você. As fontes do próprio pin continuam contando mais. Uma imagem que mostra outra coisa, ou mostra mal, também é analisada e rebaixada ou substituída.
Título original: Atmosphere Dickerson: 360 MW in Development; 110-Acre Application Scope