A primeira entrada é sempre a fonte do pin. A confiança geral é uma média ponderada de quanto cada referência sustenta os horários de início e fim usados acima; uma referência conta metade a cada 180 dias a mais em relação à mais recente.
The saved date is an estimated tracking or capacity-trajectory marker, not a verified exact opening day. Construction status follows the cited dated physical scope; no completion is inferred from elapsed targets.
Construction research 2026-10-24: Epoch’s[1] 2026-07-30 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “still under construction and not yet energized” Dated observation 2026-07-30; future trajectory rows and modeled costs are distinguished from this physical milestone.
San Angelo LIVE! confirms the 951 County Road 204 site, Cipher/Fluidstack/Anthropic partnership, and $10M municipal water foundation pledge.
TheEnergyMag reports Barber Lake's 10-year ~$3B Fluidstack lease for 168 MW (with $1.4B Google backstop) and off-grid on-site water supply.
Falta algo ou há um erro? Diga com suas palavras: um link que sustente este pin, uma data de início ou fim diferente e por quê, ou um fato que falta ou está errado. A IA confere isso com as fontes do pin, procura outras melhores e adiciona qualquer página que dê razão a você. As fontes do próprio pin continuam contando mais. Uma imagem que mostra outra coisa, ou mostra mal, também é analisada e rebaixada ou substituída.
| 2025-11-29 | As fundações do Edifício 1 são visíveis. |
|---|
| 2026-07-30 | O edifício 1 está completo, com unidades no telhado instaladas e a maioria dos chillers resfriados a ar instalados em um pátio térreo ao norte. A maioria dos 120 geradores diesel de reserva também es… |
|---|
| 2026-12-30 | O Edifício 1 Fase I está operacional: 168 MW de potência crítica de TI (244 MW brutos), executando Google TPU v7 (tipo de chip inferido, provavelmente marcado). Estimamos ~dezembro de 2026, cerca de… |
|---|
| 2027-04-30 | O Edifício 1 Fase II está operacional: 207 MW de TI crítica total (300 MW brutos). A Fase II adiciona 39 MW de TI crítica (consulte [Cipher 2025-11-20 PR](https://www.globenewswire.com/news-release/2… |
|---|
Notas de imagens de satélite da Epoch AI, em ordem de data. · fonte
Physical-stage observation dated 2026-07-30. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“still under construction and not yet energized”
Epoch’s dated 2026-07-30 assessment: still under construction and not yet energized Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“still under construction and not yet energized”
AI data-center compute infrastructure. Hardware inventory remains unpublished or not verified in this project assessment.
“AI data center”
Epoch dated observation: Site grading and civil works begin.
“Site grading and civil works begin.”
Epoch dated observation: Building 1 shell is complete, with rooftop units installed, and most…
“Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north.”
Anthropic Barber Lake in Colorado City, Texas, United States is a frontier AI data center campus operated by Cipher Mining / Anthropic reaching 207 MW of power capacity and 288,530 H100-equivalent AI accelerators. Barber Lake runs Google TPUs rather than NVIDIA GPUs: Google both supplies the chips and helped bankroll the buildout, taking an equity stake in the developer so its silicon could be deployed for Anthropic through Fluidstack.
Epoch’s 2026-07-30 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget.