Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · fonte
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · fonte
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · fonte
| Date | Observed status |
|---|---|
| 2023-01-01 | Land clearing begins, with the east campus being the first of the three. Land clearing begins for the other two campuses months after. |
| 2025-01-01 | The first building is operational. On the north campus, building 4 is operational assuming a 3-month fit-out post structural completion. |
| 2025-03-01 | Three buildings are operational. On the west campus, building 1 is operational, and on the east campus, building 7 is operational. The second building on the east campus has installed generators, but |
| 2025-11-01 | Four buildings are operational. On the west campus, building 2 is operational assuming a 3-month fit-out post structural completion. |
| 2026-01-24 | Four buildings are operational in total. A fifth building, building 5 on the north campus, is finishing installing roofside cooling. Another building on the east campus is complete but does not have s |
| 2026-06-01 | Four buildings are operational. On the north campus, building 5 is nearing structural completion but still has roofing and cooling remaining. |
| 2026-08-06 | On the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars. Building 6, a much larger building across the pond, should finish construction in |
| 2026-11-01 | Five buildings are operational. On the north campus, building 5 is operational assuming a 3-month fit-out post structural completion. |
| 2026-12-31 | Six buildings are operational. On the north campus, building 6, the larger building, is operational assuming a 3-month fit-out if it is structurally complete in September. We assume Building 6 is abou |
| 2027-12-01 | All eight AI buildings are operational. Buildings 3 and 9 are assumed to be 1.25x the power and compute of buildings 1 and 7 based on the sizing of the backup generator enclosures; building 8 is exclu |
Epoch AI satellite-imagery notes, in date order. · fonte
Em construção
Digital infrastructure: AI data-center campus buildout · Verificado em 2026-10-30
Apenas a etapa informada é destacada. Os números e datas distinguem planos de resultados demonstrados.
Epoch’s current campus estimate: 157 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 157 MW”
Physical-stage observation dated 2026-08-06. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“building 9 is under construction”
Epoch’s dated 2026-08-06 assessment: building 9 is under construction Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“building 9 is under construction”
Epoch estimates AI hardware: Huawei Ascend 910C chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Huawei Ascend 910C chips.”
Epoch dated observation: Land clearing begins, with the east campus being the first of the three.
“Land clearing begins, with the east campus being the first of the three.”
Epoch dated observation: On the north campus, building 5 is structurally complete but not…
“On the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars.”
Fotos de leitores, separadas das mídias com fontes do pin. Avalie o que você comeu ou viu e, em um pin de restaurante, marque os pratos direto na sua foto.
A primeira entrada é sempre a fonte do pin. A confiança geral é uma média ponderada de quanto cada referência sustenta os horários de início e fim usados acima; uma referência conta metade a cada 180 dias a mais em relação à mais recente.
A data salva é um rastreamento estimado ou marcador de trajetória de capacidade, não um dia de abertura exato verificado. O estado de construção segue o escopo físico datado citado; nenhuma conclusão é inferida a partir de metas decorridas.
Construction research 2026-10-24: Epoch’s[1] 2026-08-06 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “building 9 is under construction” Dated observation 2026-08-06; future trajectory rows and modeled costs are distinguished from this physical milestone.
Falta algo ou há um erro? Diga com suas palavras: um link que sustente este pin, uma data de início ou fim diferente e por quê, ou um fato que falta ou está errado. A IA confere isso com as fontes do pin, procura outras melhores e adiciona qualquer página que dê razão a você. As fontes do próprio pin continuam contando mais. Uma imagem que mostra outra coisa, ou mostra mal, também é analisada e rebaixada ou substituída.
Título original: Huawei Wuhu AI Data Center Buildout
Huawei Wuhu em Wuhu, Anhui, China, é um campus de data center de IA de ponta operado pela Huawei, atingindo 457 MW de capacidade de energia e 221.924 aceleradores de IA equivalentes ao H100. 0
A observação da Epoch de 06/08/2026 documenta a construção/instalação física restante para este edifício nomeado. Em andamento não conclui edifícios operacionais anteriores ou capacidade futura. As contagens de potência e acelerador permanecem estimativas da Epoch, e não uma classificação certificada pelo operador. Os custos de capital modelados em dólares de 2025 incluem hardware de computação e não são um orçamento de construção nativo da fonte.